← Course overview

Jenkins Academy of Applied Technology

Aerial Lifts and Scissor Lifts — Regulatory crosswalk

Aerial Lifts and Scissor Lifts · v1.0.0 · October 22, 2026

Course developed by Todd Jerome Jenkins, MS, CSP.

General-industry and construction aerial-lift and mobile-scaffold requirements. Equipment-specific instruction, practical verification, workplace authorization and related qualifications remain separate.

AreaBasisLessonsTreatment and separate evidence
AWP-001 — Identify the lift and the applicable rules1910.67; 1910.27(a); 1926.451-.454; OSHA interpretation, February 23, 2000scopeIdentify the machine, task and applicable rule before choosing training or fall protection. Identify the machine, task and applicable rule before choosing training or fall protection.
AWP-001 — Provide training for the worker’s actual duties1926.454(a)-(b); 1926.453(b)(2)(ii); 1910.67(c)(2)(ii); OSHA Aerial Lifts Fact SheettrainingMatch training, trainer qualifications and practical verification to the worker’s assigned duties. Match training, trainer qualifications and practical verification to the worker’s assigned duties.
AWP-001 — Recognize when additional training is needed1926.454(c); OSHA interpretation, February 23, 2000; OSHA Aerial Lifts Fact SheetretrainingUse changed hazards and observed performance to decide what retraining and verification are needed. Use changed hazards and observed performance to decide what retraining and verification are needed.
AWP-001 — Select a lift that fits the work1910.67(c); 1926.453(b); 1926.451(a), (f); OSHA Aerial Lifts Fact SheetselectionChoose the correct model and accessories using the actual task, surface, environment and load. Choose the correct model and accessories using the actual task, surface, environment and load.
AWP-001 — Inspect the machine and test its controls1910.67(c)(2)(i); 1926.453(b)(2)(i); 1926.451(f)(3)-(4); OSHA Aerial Lifts Fact SheetinspectionComplete the required checks, identify defects and prevent use until safe operation is restored. Complete the required checks, identify defects and prevent use until safe operation is restored.
AWP-001 — Check the work area and establish stable support1910.67(c)(2)(vii); 1926.453(b)(2)(vii); 1926.451(c), (f); 1926.452(w)supportVerify the route, floor or ground support, stability controls and changing site conditions. Verify the route, floor or ground support, stability controls and changing site conditions.
AWP-001 — Use the required fall protection in boom lifts1910.67(c)(2)(iii)-(v); 1910.140; 1926.453(b)(2)(iii)-(v); 1926.502(d)-(e)boom_fallsUse a compatible approved system and anchor, inspect it and keep a safe position inside the platform. Use a compatible approved system and anchor, inspect it and keep a safe position inside the platform.
AWP-001 — Protect workers on scissor-lift platforms1910.27(a); 1926.451(g); 1926.452(w); OSHA interpretation, February 23, 2000scissor_fallsKeep the complete guardrail system effective and resolve any additional fall-protection requirement for the actual model. Keep the complete guardrail system effective and resolve any additional fall-protection requirement for the actual model.
AWP-001 — Manage capacity, materials and falling objects1910.67(c)(2)(vi); 1926.453(b)(2)(vi); 1926.451(f)(1), (h); OSHA Aerial Lifts Fact SheetloadsCheck all load limits and protect people from material that could fall or affect stability. Check all load limits and protect people from material that could fall or affect stability.
AWP-001 — Move and position the lift safely1910.67(c)(2)(viii), (xii); 1926.453(b)(2)(viii), (xii); 1926.452(w)travelUse only permitted travel modes, inspect the full route and keep occupants and nearby people informed. Use only permitted travel modes, inspect the full route and keep occupants and nearby people informed.
AWP-001 — Keep clear of electrical hazards1910.67(b)(4), (c)(2)(xi); 1910.333(c)(3); 1926.451(f)(6); 1926.416; OSHA Aerial Lifts Fact SheetelectricalEstablish voltage-appropriate clearance and electrical controls before positioning the lift. Establish voltage-appropriate clearance and electrical controls before positioning the lift.
AWP-001 — Control crushing hazards, traffic and weather1926.454(a); 1926.451(f)(8), (12); OSHA Aerial Lifts Fact Sheetcrushing_weatherControl the whole movement envelope, protect nearby people and stop when weather or site conditions exceed the plan. Control the whole movement envelope, protect nearby people and stop when weather or site conditions exceed the plan.
AWP-001 — Prepare emergency lowering and rescue1910.67(c)(2)(ix); 1926.453(b)(2)(ix); 1910.140(c)(21); 1926.502(d)(20); manufacturer proceduresemergenciesVerify trained emergency-lowering help, communication and any required prompt-rescue arrangements before elevation. Verify trained emergency-lowering help, communication and any required prompt-rescue arrangements before elevation.
AWP-001 — Verify readiness, shutdown and records1910.67; 1910.147; 1926.451-.454; 1926.417; manufacturer proceduresverificationRecord the actual readiness decision, preserve restrictions and leave equipment safely secured. Record the actual readiness decision, preserve restrictions and leave equipment safely secured.

Sources

Federal OSHA sources reviewed October 22, 2026. Confirm the actual work, jurisdiction and applicable additional requirements. Agency guidance supports planning; it is distinguished from mandatory standard text.