Two worker knowledge tracks are provided. They have separate identities, thresholds, trainer/inspection wording and records. Introductory coverage does not authorize specialized methods or establish actual system skills. Task-specific instruction is required before any method/equipment outside the reviewed assignment is used.

Construction — all eight 1926.503(a)(2) areas

ID / provisionTraining topicCore coverageActual instruction still required
C01
1926.503(a)(2)(i)
Nature of work-area fall hazardsF01, F02Actual task, access, surfaces, edges/holes, fall paths and changing conditions.
C02
1926.503(a)(2)(ii)
Erect, maintain, disassemble and inspect systemsF03, F06, F07Actual installation/removal and maintenance/inspection methods; assigned trained roles and protected access.
C03
1926.503(a)(2)(iii)
Use/operation of systems to be usedF03–F08Actual conventional systems; nets/restricted methods need additional specific instruction before use.
C04
1926.503(a)(2)(iv)
Employee roles in safety monitoring when usedF08No monitor assignment authorized by core; actual eligible method and role instruction required if adopted.
C05
1926.503(a)(2)(v)
Mechanical-equipment limitations on low-slope roofingF08Actual eligible roofing method and equipment limits/geometry; specialized supplement pending if used.
C06
1926.503(a)(2)(vi)
Equipment/material handling/storage and overhead protectionF06, F07Actual storage/handling, falling-object controls and safe overhead-protection erection/removal.
C07
1926.503(a)(2)(vii)
Employee roles in fall-protection plansF08Actual separately reviewed plan and role; no alternative-plan authorization or infeasibility exception granted.
C08
1926.503(a)(2)(viii)
Subpart M standardsF01–F10Actual applicable task provisions and system criteria; employer instruction closes specific details.

General industry — four fall topics and four equipment provisions

ID / provisionTraining topicCore coverageActual instruction still required
G01
1910.30(a)(3)(i)
Nature and recognition of work-area fall hazardsF01, F02Actual tasks, surfaces, access, fall paths and hazards.
G02
1910.30(a)(3)(ii)
Procedures to minimize hazardsF02, F03, F07Actual chosen protections, transitions and stop conditions.
G03
1910.30(a)(3)(iii)
Install, inspect, operate, maintain and disassemble personal systemsF04, F06, F07Actual models/components and protected installation/removal/maintenance methods.
G04
1910.30(a)(3)(iv)
Correct use, hook-up, anchoring/tie-off, inspection and storageF04–F07Actual approved configuration, manufacturer limits, fit and observed safe use.
G05
1910.30(b)(1)
Care, inspection, storage and use of covered equipmentF06, F08All actual covered equipment before use, including items beyond generic core.
G06
1910.30(b)(2)
Dockboard placement and securingF08Actual board/interface instruction and safe verification before assigned use; core is introductory.
G07
1910.30(b)(3)
Rope-descent rigging and useF08Outside this core’s qualification; specific 1910.27 training/arrangements required before assignment.
G08
1910.30(b)(4)
Designated-area setup and useF08No method authorization by core; actual eligibility, setup/use and user training required if adopted.

Process and evidence distinctions

TopicConstruction basisGeneral-industry basisPending employer evidence
Scope/common edge trigger1926.500; 1926.501(b)(1): 6 feet or more1910.28(b)(1)(i): 4 feet or moreExact industry/task/jurisdiction and allowed protection; no universal threshold.
Surfaces, holes, dangerous equipment1926.501(a)(2), (b)(4), (8)1910.22; 1910.28(b)(3), (6)Actual surface support, holes, lower hazards and protection even below a common edge threshold.
Trainer/understandable instruction1926.503(a): competent person qualified in relevant areas; OSHA training policy1910.30(a)(2): qualified person; (d) understandable instructionActual subject capability, authority/qualifications where required, suitable language and timely trainer access.
Personal system compatibility, anchors and clearance1926.502(d), including (8), (15), (16), (23)1910.140(c)–(d), including (11)–(13)Actual complete compatible system, anchor design/capacity/installation, free-fall/performance limits and clear path.
Routine personal-system inspection1926.502(d)(21): before each use1910.140(c)(18): before initial use during each workshiftActual manufacturer checks and any stronger employer policy; inspections do not become interchangeable by copying a form.
Impact-loaded equipment1926.502(d)(19)1910.140(c)(17)Immediate removal, required competent-person suitability determination and manufacturer disposition; no automatic reuse.
Prompt rescue1926.502(d)(20): prompt rescue or assured ability to self-rescue1910.140(c)(21): prompt rescueVerified scenario-specific method, trained capability, resources/access/communications; no assumed fire-service capability or universal time promise.
Training records1926.503(b): employee identity, dates, trainer/employer signature; latest certification; specified prior-training adequacy date1910.30 itself does not prescribe that construction certification formatActual completed training/skills and applicable record duties; separate role forms identify which is required versus Academy evidence design.
Retraining1926.503(c)1910.30(c)Workplace/system changes and understanding/use deficiencies; no universal annual renewal asserted by these base provisions.
Restricted methods/specialized workRoofing/warning/monitoring/CAZ/alternative plan have specific conditions; other subparts govern some workDesignated areas/roofs, dockboards/RDS and other access have specific conditions/trainingSeparate actual review and instruction. Nets, restricted methods, ladders, scaffolds, lifts, steel, utilities, maritime and project-specific qualifications are not granted by the core.
Event investigation/learningEmployer program commitment; 1926.502(k)(10) is an alternative-plan-specific provisionEmployer learning/change process plus applicable separate reporting dutiesCare and control first; preserve evidence, learn from work design and verify corrective-action effectiveness.
Assessment/LMS designAcademy: 80% (15/18) plus all 10 critical correctSame rule, separate course state and assessment banksSubject-matter/assessment review, actual LMS/browser/pilot testing; online passed means this track’s knowledge only.

Five historical uploaded RAVS inputs

The 2022 export mixes examples from multiple industries. Its general-industry edge wording is not used to replace the current at-or-above trigger. Its alternative-plan citation is kept in context. Verify current client requirements separately.

InputAreaMappingInterpretation/evidence
RAV-1Training and recordsBoth F01, F10; employer training recordApply competent-person-qualified training and certification for construction; qualified-person training and actual evidence for general industry.
RAV-2RetrainingBoth F10; training/retraining recordWorkplace/equipment changes and knowledge/use deficiencies trigger appropriate retraining.
RAV-3Correct industry/state/task protection triggerBoth F01, F02, F08; task planCurrent 4-foot/6-foot common edge starting points are at or above the stated height; special tasks/hazards differ. Historical multi-industry wording is not universal authority.
RAV-4Investigate falls and improve plansBoth F10; employer learning/change processEmployer program commitment covers events/normal work; 1926.502(k)(10) has specific alternative-plan context.
RAV-5Prompt rescue readinessBoth F09; rescue worksheetVerify actual trained capability, method, resources and access before arrest work; do not assume local responders can perform it.

Sources reviewed October 21, 2026

The federal regulations are the baseline. Interpretation letters explain their context. Actual manufacturer instructions, drawings, task provisions, State Plan and project/client requirements must be supplied and reviewed before use.

Development sources read: SHP-003 Fall Protection Program v0.2 and the five-question RAVS_Requirements (15).pdf, exported July 22, 2022. The program’s construction base informs this draft. General industry is a separate regulatory track; it is not treated as already approved by that construction program. State supplements, current client acceptance and employer implementation are not established by this bundle. Historical contractor responses/results are not transferred.