Machine Assisted Concrete Slab Removal JHA
A JHA breaks the work into steps, hazards and controls. Use this example to build a draft for your actual job and review it with your crew.
Just need the example? Download it here.For the crew
You know the work. Let’s turn that experience into a plan your crew can talk through. Start with today’s job, then check the steps together.
Let’s build your JHA.
Step 1 of 4 · Working draft
Your job
Tell Jenkins what you’re planning and where the work will happen. Use the actual job details.
Use the published example’s suggestions when they fit your task, or write your own steps. These are planned controls, not verified worksite conditions.
Describe an observable step, how someone could be harmed, and the control that acts on that hazard. Identify who checks it and what evidence is needed.
Walk through the plan with the people doing the work. Resolve missing controls and agree who checks them. Moving to the next step does not approve the work.
Confirm people, equipment and emergency arrangements
Record changes, checks, and open actions
Walk the work area, review with the crew, and resolve missing controls. Follow the required approval process. This tool does not judge completeness, verify signatures or authorize work.
Print your own JHA by signing in, or contribute the selected structured categories as a guest. Signing in does not require research participation. Written job details are processed to prepare your export and are stored on our server only if you save to your private company library.
Research purpose, data fields, retention and withdrawal · Privacy notice
Sign-in uses a free account. Your tab draft is retained for the return from sign-in.
Hosted organization saving requires active jSMS access and a company workspace. View jSMS plans.
The export uses landscape pages, task-only continuation pages and a Page X of Y footer in current Chrome or Edge. Review every page. Opening an export is not proof that the JHA was printed or used. The PDF includes its research choice and reference; the private withdrawal link stays in the export’s screen-only receipt.
Device storage and other draft options
Device copies may contain private job information. Clear them when using a shared device.
Your entries stay in this working draft as you move between steps. Required field checks, employer review and work authorization remain separate.
Your Machine Assisted Concrete Slab Removal JHA
Walk through the job in order. Use these possible hazards, planned controls and checks to start a conversation about your actual work.
011. Confirm the slab removal release
Possible hazards: An assumed nonstructural slab or concealed service can become a collapse or utility-strike event.
Planned controls: Demolition lead obtains the written engineering survey and current utility/material review for the marked slab. Resolve connections to foundations and adjacent structures, define the depth/removal boundary and establish required isolation before mobilizing the breaker.
Check before work: Lead checks the marked limit against survey and utility-release records.
022. Prepare machine access and separation
Possible hazards: An unstable operating surface or pedestrian entry can cause overturning or crushing.
Planned controls: Equipment lead selects the actual machine and approved breaker/bucket arrangement and checks support and travel conditions. Mark the operating, fragment and debris-transfer boundaries; establish a protected spotter position and a positive stop/contact method. Separate haul traffic and other trades.
Check before work: Operator and lead check the work route, boundaries and spotter communication.
033. Verify attachment and exposure controls
Possible hazards: A damaged attachment can fail; an unsuitable cab or dust method can expose the crew to silica.
Planned controls: Operator completes the manufacturer’s pre-use and attachment checks and rejects defects. Silica competent person verifies the Table1 heavy-equipment fracture/demolition method or the employer’s alternative assessment route; confirm cab requirements and any outside-worker dust suppression. Provide noise protection and planned slurry handling.
Check before work: Operator records defects; silica competent person checks the actual cab and exposure-control setup.
044. Break the marked slab in controlled sections
Possible hazards: Unplanned fragmentation can throw debris, undermine support or expose an unknown connected element.
Planned controls: Operator follows the released breaker method and removal progression, keeping people outside the operating boundary. The competent person reviews changing ground, loosened material and adjacent supports as work advances. Stop for unexpected reinforcement, voids, services or slab movement rather than probing farther with the breaker.
Check before work: Demolition lead records changing conditions and confirms the next section remains within the release.
055. Change attachment and remove debris
Possible hazards: Stored hydraulic energy, falling attachments or unstable debris can crush workers during the phase change.
Planned controls: Use the actual manufacturer’s parking, isolation and attachment-change method with the attachment supported and workers protected. Verify the compatible bucket’s secure connection before use. Load debris within the machine and container limits on the controlled haul route; keep workers clear of suspended or shifting pieces.
Check before work: Authorized operator verifies the attachment connection and lead checks debris-transfer separation.
066. Leave a protected removal area
Possible hazards: Exposed edges, loose fragments or dusty cleanup can injure the next crew.
Planned controls: Remove or stabilize remaining loose material using the planned method and inspect the yard’s actual condition. Protect the opened boundary and retain any isolation or access restriction. Collect dust/slurry and hand over the removal limits and findings; further excavation requires a separate release.
Check before work: Competent person records final findings and lead confirms waste and access handover.
Example scope and starting conditions
A trained equipment crew will break and remove a released outdoor nonstructural slab on grade in a closed building yard. An excavator-mounted breaker fractures the marked slab; after the equipment is made safe under its instructions, a compatible bucket handles debris. The operation does not include digging below the released slab limit. This fictional learning example describes planned controls; it records no actual inspection or work authorization.
- The written demolition survey and utility/material review establish slab function, exact removal limits, connected elements and any required isolation before machine disturbance.
- The actual excavator, approved attachments, ground support, movement routes and exclusion boundary are selected for the yard and surrounding structures.
- This is partial coverage of concrete demolition and removal. Suspended slabs, live utilities, excavation, crushing plants, whole-structure demolition and handheld breaker work are excluded.
Know when to pause
- The slab reveals uncharted services, connected structural elements, reinforcement or a void beyond the survey assumptions.
- Ground, adjacent supports or debris conditions change, or someone enters the equipment/fragment boundary.
- An attachment defect, communication failure or loss of the selected silica controls prevents the released method.
After a pause, correct the condition, reassess the work, and obtain required authorization before restarting.
Free example and template
No account required. The worked example contains planned controls. The blank template is for your own work; neither includes fabricated inspection results, signatures or approval.
Need help? Ask Jenkins
Jenkins · Your Safety Concierge
What brings you here today? Choose what you’re working on, or tell Jenkins about your situation.
Jenkins matches your words to published starting points. Keep names and private job details in your working draft. Suitable free resources come first.
For managers
Does the team have what it needs to carry out the plan? Give the crew time, equipment and support, and make it clear who will resolve anything that is missing.
Manager checks and supporting resources
Confirm the people doing the work have the time, equipment, information and support to carry out the plan. Agree who checks the controls and who resolves open actions.
Questions to resolve before work
- What evidence establishes that this slab can be removed without affecting foundations, adjacent supports or embedded services?
- How will workers remain clear of the equipment, fragment throw and debris-handling route during each operating phase?
- Which silica-control method applies to the actual excavator task and any employees outside its cab?
Training and qualifications to confirm
- Equipment and attachment-specific operator instruction, including permitted use, safe attachment changes, isolation and spotter communication for the actual machine.
- Supervisor and crew instruction in demolition-release boundaries, continuing hazard review, equipment/pedestrian separation and the applicable silica-control plan.
Confirm the actual training evidence for the assigned people. A toolbox talk does not establish competence.
Decisions that change the plan
Does the existing concrete saw-cutting example cover breaking and removal?
No. It expressly ends with protected cuts and excludes slab breaking, lifting and excavation. This operation creates fragments with powered mobile equipment and then changes equipment state to handle debris; it needs a demolition release and machine separation controls.
What must the crew record for actual use?
Record the written survey and utility/material findings, marked slab and depth limits, machine/attachment identities, support and route checks, exposure-control basis, communication and exclusion arrangements, changing-condition findings, actual attachment-change verification and final access restrictions.
Keep planning connected
Resources that support this JHA
Additional tools for task planning and safe work. Start with the free resources; explore paid options only when they meet an additional need.
Toolbox talks for the work
Prepare a practical crew discussion.
Demolition: Verify Before Disturbing →Mobile Equipment: Separate People from Movement →Silica: Verify Dust Controls Before Cutting →Safety program resources
Review procedures, roles, and requirements.
Browse the existing catalog and confirm the scope and purchase availability of each program.
Browse safety programs →Paid service · Availability
Task-specific training and qualifications
Explore applicable training and qualification needs.
Task-specific training services are not currently available to book here. Start with the free training-needs lookup; a toolbox talk or online course alone does not establish competence or employer authorization.
Review training needs · Free →People, equipment, emergency arrangements and open actions are recorded in the guided JHA’s Crew review step.
Open the crew review step →For safety professionals
How do we know the planning process and controls are working? Connect what the crew reports with field checks, risk decisions and the evidence behind your system.
Industry context, SIF, control verification and AHA review
Guidance and evidence
Review the method, risk decisions and evidence behind the plan. Use the actual jurisdiction, equipment instructions, employer process and project requirements.
Task-by-task control and verification rationale
1. Confirm the slab removal release
Hazard: An assumed nonstructural slab or concealed service can become a collapse or utility-strike event.
Control: Demolition lead obtains the written engineering survey and current utility/material review for the marked slab. Resolve connections to foundations and adjacent structures, define the depth/removal boundary and establish required isolation before mobilizing the breaker.
Verification: Lead checks the marked limit against survey and utility-release records.
Why this belongs in the analysis: The machine’s ability to break concrete does not prove the concrete is safe to remove.
2. Prepare machine access and separation
Hazard: An unstable operating surface or pedestrian entry can cause overturning or crushing.
Control: Equipment lead selects the actual machine and approved breaker/bucket arrangement and checks support and travel conditions. Mark the operating, fragment and debris-transfer boundaries; establish a protected spotter position and a positive stop/contact method. Separate haul traffic and other trades.
Verification: Operator and lead check the work route, boundaries and spotter communication.
Why this belongs in the analysis: Separation must cover the whole machine and fragment envelope, not only the tracks.
3. Verify attachment and exposure controls
Hazard: A damaged attachment can fail; an unsuitable cab or dust method can expose the crew to silica.
Control: Operator completes the manufacturer’s pre-use and attachment checks and rejects defects. Silica competent person verifies the Table1 heavy-equipment fracture/demolition method or the employer’s alternative assessment route; confirm cab requirements and any outside-worker dust suppression. Provide noise protection and planned slurry handling.
Verification: Operator records defects; silica competent person checks the actual cab and exposure-control setup.
Why this belongs in the analysis: Excavator breaking has different Table1 conditions from handheld jackhammer work.
4. Break the marked slab in controlled sections
Hazard: Unplanned fragmentation can throw debris, undermine support or expose an unknown connected element.
Control: Operator follows the released breaker method and removal progression, keeping people outside the operating boundary. The competent person reviews changing ground, loosened material and adjacent supports as work advances. Stop for unexpected reinforcement, voids, services or slab movement rather than probing farther with the breaker.
Verification: Demolition lead records changing conditions and confirms the next section remains within the release.
Why this belongs in the analysis: A changed condition requires a new decision before the next machine impact.
5. Change attachment and remove debris
Hazard: Stored hydraulic energy, falling attachments or unstable debris can crush workers during the phase change.
Control: Use the actual manufacturer’s parking, isolation and attachment-change method with the attachment supported and workers protected. Verify the compatible bucket’s secure connection before use. Load debris within the machine and container limits on the controlled haul route; keep workers clear of suspended or shifting pieces.
Verification: Authorized operator verifies the attachment connection and lead checks debris-transfer separation.
Why this belongs in the analysis: Changing from breaking to lifting changes both equipment state and the line of fire.
6. Leave a protected removal area
Hazard: Exposed edges, loose fragments or dusty cleanup can injure the next crew.
Control: Remove or stabilize remaining loose material using the planned method and inspect the yard’s actual condition. Protect the opened boundary and retain any isolation or access restriction. Collect dust/slurry and hand over the removal limits and findings; further excavation requires a separate release.
Verification: Competent person records final findings and lead confirms waste and access handover.
Why this belongs in the analysis: A cleared slab area is not automatically an approved excavation or traffic route.
Compare control wording
| Needs improvement | More useful for this scenario |
|---|---|
| Break it out carefully and keep people back. | Demolition lead releases the exact removal limit and a marked machine/fragment boundary; operator stops when actual conditions differ from the survey. |
| Use water like a handheld breaker. | Silica competent person selects and verifies the actual heavy-equipment Table1 method or alternative exposure route, including cab and outside-worker conditions. |
Common questions
Can this example be used as a JSA?
Adapt its Task | Hazard | Control analysis to the employer’s JSA format and the actual work. Confirm the assigned checks and record real findings before relying on the plan.
What changes if the project requires an AHA?
Use the project’s governing AHA format, risk method, supporting records and acceptance process. The published formwork AHA illustrates that additional structure; this JHA does not establish an AHA risk rating or acceptance.
Are these resources part of a paid course?
This walkthrough, browser draft builder and downloads are free public resources, separate from Academy course enrollment.
References and source note
- OSHA 1926.850 Demolition preparatory operations
- OSHA 1926.859 Mechanical demolition and continuing inspections
- OSHA 1926.1153 Table1 Heavy-equipment fracture and demolition
Original instructional scenario with planned controls. Primary references support hazard planning. Use actual equipment and product instructions, project design and employer requirements to establish field criteria. This example supplies no inspection findings or work authorization. Use actual equipment instructions and site requirements alongside these references. Reference review: October 9, 2026.
Developed by Todd Jerome Jenkins, MS, CSP · Edition v1.0 · October 13, 2026