Captured Stick Curtain Wall Installation JHA: Worked Example & Free Template

Plan captured stick curtain wall installation with a defined worksite, six task steps, control verification, a worked example and editable templates.

By Todd Jerome Jenkins · Edition v1.0 · October 13, 2026

Get the example and template Build your draft

First, describe the work and worksite

A glazing crew assembles one mechanically captured stick curtain-wall bay on a new building, then sets its specified IGU. Protected upper-floor work positions, lifting arrangements and the project-designed anchor layout are already released. This fictional learning example describes planned controls; it records no actual inspection or work authorization.

  • Partial curtain-wall and elevated-glazing coverage: one site-assembled captured bay, with no factory unitized-module erection or structural-silicone bonding.
  • The accepted system details identify anchors, member splices, glass supports, drainage and pressure-plate retention.
  • Work-platform erection and lifting-system setup are separately accepted; the area below is closed to other work.

Questions before work

  • Who accepts the designed anchors, splice arrangement and temporary restraint for the partly assembled bay?
  • What prevents falls and dropped components throughout assembly, glazing and fixing inspection?
  • Which exact system checks release member support and then release the glass-handling equipment?

Build the analysis one step at a time

What will the worker do? How could someone be harmed? What prevents or reduces that exposure? Who checks the control, and when?

1. Release the bay design and work area

Hazard: Unaccepted anchors or conflicting work below can turn a small assembly into a falling load.

Control: Review current system and project drawings, member labels and support sequence. Verify protected access, exclusion below and the accepted substrate before taking components to the edge.

Verification: Lead records drawing revision, substrate release and the assigned observer for the exclusion area.

Why this belongs in the analysis: A familiar-looking curtain-wall profile does not establish the required anchor arrangement.

2. Stage individual members and glazing

Hazard: Long profiles or leaning glass can slide; unsupported reaching exposes installers to falls and cuts.

Control: Use secured staging matched to component weights. Maintain clear access and the planned lift path; arrange tools and members within the protected reach envelope.

Verification: Crew checks staging restraint and access before moving the first member to the bay.

Why this belongs in the analysis: Staging must remain safe as components are removed and the remaining load distribution changes.

3. Assemble and restrain the stick frame

Hazard: A partly connected mullion or transom may rotate or drop before the bay becomes stable.

Control: Install members in the approved sequence while maintaining their designed temporary restraint. Fit specified anchors and splices; do not release support on the strength of an alignment fastener.

Verification: Responsible installer verifies connection and restraint acceptance before transferring support to the frame.

Why this belongs in the analysis: The bay acquires its support progressively; visual alignment is not proof of stability.

4. Prepare glass supports and set the IGU

Hazard: Missing support blocks, glass-edge contact or premature suction release can cause pane failure or a fall.

Control: Inspect the approved glass supports and contact surfaces. Set the identified pane using the accepted handling plan, keep workers out of pinch points and maintain handling restraint until designated mechanical retention is complete.

Verification: Glazing lead checks pane identity and bearing, and confirms handling restraint remains engaged for the final retention stage.

Why this belongs in the analysis: The load needs the designed support and retention rather than friction against a gasket.

5. Complete captured retention and weather details

Hazard: An incomplete pressure plate can leave glass insecure; careless finishing can obstruct the drainage path.

Control: Complete the specified pressure plates, fastenings, gaskets and seals from protected positions. Apply the actual system acceptance criteria and preserve its drainage details; quarantine missing or damaged parts.

Verification: Record retention and drainage inspections against the actual system release criteria before authorizing handling-device release and fitting covers.

Why this belongs in the analysis: Decorative caps can hide missing retention components without providing their function.

6. Accept the bay and release the work zone

Hazard: Unrecorded incomplete joints or loose components expose the next crew and people below.

Control: Inspect the finished bay and account for tools and offcuts. Record unfinished interfaces, then remove temporary support and reopen the area only through the agreed acceptance sequence.

Verification: Supervisor confirms bay status, support release and the separate decision to reopen below.

Why this belongs in the analysis: A glazed appearance does not tell another trade which connections remain incomplete.

What does a useful control look like?

Needs improvementMore useful for this scenario
Work carefully and wear PPE.Install members in the approved sequence while maintaining their designed temporary restraint. Fit specified anchors and splices; do not release support on the strength of an alignment fastener.
Check that everything is ready.Review current system and project drawings, member labels and support sequence. Verify protected access, exclusion below and the accepted substrate before taking components to the edge.

Decisions that change the analysis

How is this different from unitized curtain-wall installation?

This bay is built from separate members on site and then mechanically captures a separate pane. The unitized example lifts a factory-built module; its module-support and connection release do not cover this progressive assembly sequence.

What must the crew record for actual use?

Identify the actual equipment and work boundaries, responsible people, applicable criteria, inspection findings and open actions. Resolve changes with affected crews and obtain required project authorization before work.

Agree when the crew will pause

  • Pause for changed anchor substrate, missing member restraint, glass damage, incomplete retention or loss of the exclusion below.
  • Reassess if the work changes to a unitized module, structural bond, unprotected platform or different system.

After a pause, correct the condition, reassess the work, and obtain required authorization before restarting. Keep unresolved actions visible.

Download the worked example and free template

No account required. The worked example contains planned controls. The blank template is for your own work; neither includes fabricated inspection results, signatures or approval.

Your editable working copy

Build and download your draft

Start blank or load the learning example. Replace its assumptions with your actual conditions and involve the people doing the work. Your entries stay in this browser tab; download a copy before leaving or refreshing.

1. Describe your work and site

2. Work through each task

Describe an observable step, how someone could be harmed, and the control that acts on that hazard. Identify who checks it and what evidence is needed.

Task 1

3. Record changes, checks, and open actions

Walk the work area, review with the crew, and resolve missing controls. Follow the required approval process. This tool does not judge completeness, verify signatures or authorize work.

Open the downloaded file in a browser, then use Print → Save as PDF for a printable copy.

Training needs to confirm

  • Train installers on the accepted stick-system member support, anchorage, glazing retention and inspection sequence.
  • Verify handling, protected access and dropped-object control competencies for the actual elevated work positions.

Confirm applicable qualifications, task instruction and actual training evidence for the people assigned. Related toolbox talks support toolbox talks; they do not establish competence.

Common questions

Can this example be used as a JSA?

Adapt its Task | Hazard | Control analysis to the employer’s format and actual conditions. The example is a teaching aid, not evidence that controls were checked.

What changes if the project requires an AHA?

Use the governing AHA format, risk method, supporting records and acceptance process. The published formwork AHA demonstrates that additional structure; changing a JHA title does not supply it.

Are these resources part of a paid course?

This walkthrough, browser draft builder and downloads are free public resources, separate from Academy course enrollment.

References and source note

Original instructional scenario with planned controls. Primary references support hazard planning. Use actual equipment and product instructions, project design and employer requirements to establish field criteria. This example supplies no inspection findings or work authorization. Use actual equipment instructions and site requirements alongside these references. Reference review: October 9, 2026.