Free worked example · Task | Hazard | Control

Precast Hollow Core Floor Erection JHA: Worked Example & Free Template

Plan precast hollow core floor erection with a defined worksite, six task steps, control verification, a worked example and editable templates.

By Todd Jerome Jenkins · Edition v1.0 · October 9, 2026

Get the example and template Build your draft

First, describe the work and worksite

A specialist precast erection crew will crane-set identified prestressed hollow-core floor planks on released bearing lines in a new building. Permanent joint work and subsequent construction loading are later activities. This fictional learning example describes planned controls; it records no actual inspection or work authorization.

  • The producer’s erection documents establish member identity, handling attachments, bearing, temporary support and sequence.
  • Open edges and incomplete floor bays have a planned fall-protection and rescue arrangement.
  • This excludes double tees, wall panels, field cutting of strands, core drilling and unplanned stockpiling on placed planks.

Questions before work

  • How are plank identity, lift attachments and bearing requirements verified?
  • What temporary supports and permitted walk-on conditions apply at each stage?
  • Who releases the installed floor for later trades and loading?

Build the analysis one step at a time

What will the worker do? How could someone be harmed? What prevents or reduces that exposure? Who checks the control, and when?

1. Release bearings and sequence

Hazard: An incomplete bearing or missing shore can lead to plank collapse.

Control: Erection lead verifies receiving supports, specified bearing details and temporary shoring against the producer’s current erection documents. Keep the lift on hold for unresolved support geometry.

Verification: Lead records receiving conditions before the first plank lift.

Why this belongs in the analysis: Member delivery does not establish the bearing’s readiness.

2. Inspect and rig the plank

Hazard: Damaged prestressed concrete or an incompatible clamp can fail during lifting.

Control: Qualified rigging personnel verify member marks, damage status and the producer’s specified lifting system. Use its required safety devices and attachments; refer damage or uncertain handling points for technical disposition.

Verification: Rigger compares plank and gear identification with the handling instructions.

Why this belongs in the analysis: A wall-panel insert method is not automatically a hollow-core method.

3. Clear and lift

Hazard: A long plank can rotate or strike the erection crew.

Control: Control the travel path and access below, use agreed crane signals and manage orientation from planned safe positions. Keep personnel clear of the suspended member and do not improvise riding or guidance from beneath it.

Verification: Lift lead confirms the path before each pickup.

Why this belongs in the analysis: Plank length creates a swing exposure beyond the hook position.

4. Seat the plank

Hazard: Misaligned bearing or a trapped hand can cause crushing or loss of support.

Control: Land in the documented sequence onto the specified bearing and supports. Use positioning tools and protected receiving positions; verify full required seating and stability before releasing lifting equipment.

Verification: Erection lead checks both bearing ends against the current criteria.

Why this belongs in the analysis: A plank touching one support is not a verified landing.

5. Protect the developing floor

Hazard: Open joints, edges or a partly supported plank can cause falls or overload.

Control: Maintain the stage-specific fall protection, opening protection and access limits. Permit walking or material placement only under the producer/design release for that erection stage; keep unapproved loads off the floor.

Verification: Lead checks protection and load restrictions after each completed section.

Why this belongs in the analysis: A visually continuous floor can still have incomplete structural work.

6. Hand over for joint work

Hazard: Later crews may assume the planks are fully accepted or cut prestressing steel.

Control: Identify unfinished connections, keyway grouting, topping and support restrictions. Mark any planned openings and require producer/engineer approval for alterations; transfer the actual stage release to the next crew.

Verification: Receiving lead confirms restrictions before joint work or loading.

Why this belongs in the analysis: Prestressed members require a controlled alteration process.

What does a useful control look like?

Needs improvementMore useful for this scenario
Work carefully and wear PPE.Control the travel path and access below, use agreed crane signals and manage orientation from planned safe positions. Keep personnel clear of the suspended member and do not improvise riding or guidance from beneath it.
Check that everything is ready.Erection lead verifies receiving supports, specified bearing details and temporary shoring against the producer’s current erection documents. Keep the lift on hold for unresolved support geometry.

Decisions that change the analysis

Can a service opening be cut wherever a core looks clear?

No. Hollow-core openings and strand effects need the producer’s and project engineer’s approved details. This erection analysis authorizes no drilling, cutting or prestressing alteration.

What must the crew record for actual use?

Identify the actual equipment and work boundaries, responsible people, applicable criteria, inspection findings and open actions. Resolve changes with affected crews and obtain required project authorization before work.

Agree when the crew will pause

  • Damaged member, unsuitable lifting gear or bearing mismatch.
  • Temporary support or fall protection cannot be maintained.
  • An unplanned opening, stockpile or altered erection sequence is requested.

After a pause, correct the condition, reassess the work, and obtain required authorization before restarting. Keep unresolved actions visible.

Download the worked example and free template

No account or paid membership required. The worked example contains planned controls. The blank template is for your own work; neither includes fabricated inspection results, signatures or approval.

Your editable working copy

Build and download your draft

Start blank or load the learning example. Replace its assumptions with your actual conditions and involve the people doing the work. Your entries stay in this browser tab; download a copy before leaving or refreshing.

1. Describe your work and site

2. Work through each task

Describe an observable step, how someone could be harmed, and the control that acts on that hazard. Identify who checks it and what evidence is needed.

Task 1

3. Record changes, checks, and open actions

Walk the work area, review with the crew, and resolve missing controls. Follow the required approval process. This tool does not judge completeness, verify signatures or authorize work.

Open the downloaded file in a browser, then use Print → Save as PDF for a printable copy.

Training needs to confirm

  • Member-specific handling, bearing checks and erection-stage access instruction.
  • Applicable crane/rigger/signal roles and fall-protection training for the actual operation.

Confirm applicable qualifications, task instruction and actual training evidence for the people assigned. Related toolbox talks support crew discussion; they do not establish competence.

Common questions

Can this example be used as a JSA?

Adapt its Task | Hazard | Control analysis to the employer’s format and actual conditions. The example is a teaching aid, not evidence that controls were checked.

What changes if the project requires an AHA?

Use the governing AHA format, risk method, supporting records and acceptance process. The published formwork AHA demonstrates that additional structure; changing a JHA title does not supply it.

Are these resources part of a paid course?

This walkthrough, browser draft builder and downloads are free public resources, separate from Academy course enrollment.

References and source note

Original instructional scenario with planned controls. Primary references support hazard planning. Use actual equipment and product instructions, project design and employer requirements to establish field criteria. Use actual equipment instructions and site requirements alongside these references. Reference review: October 9, 2026.

Prepare the crew discussion

Related work activities