Free worked example · Task | Hazard | Control

Structural Steel Column Erection JHA: Worked Example & Free Template

Plan structural steel column erection with a defined worksite, six task steps, control verification, a worked example and editable templates.

By Todd Jerome Jenkins · Edition v1.0 · October 9, 2026

Get the example and template Build your draft

First, describe the work and worksite

A specialist erection crew will crane-set one identified steel building column onto a released foundation and anchor-rod arrangement. The column’s designed leveling, anchorage and any required guys or braces will be installed before crane support is released. This fictional learning example describes planned controls; it records no actual inspection or work authorization.

  • The steel erector receives required written foundation-strength and anchor-rod modification notifications before erection begins.
  • The released lift, receiving support and column stability arrangement govern this member; actual load/rigging capacities are not supplied by this example.
  • Beam connecting, bay plumbing, final connection work and repairing or field-modifying anchor rods are separate scopes.

Questions before work

  • Which written foundation and anchor-rod notifications must the erector receive before this lift?
  • Who confirms the base, leveling arrangement and column anchorage match the released design?
  • What guys or braces does the competent-person evaluation require before crane support is released?

Build the analysis one step at a time

What will the worker do? How could someone be harmed? What prevents or reduces that exposure? Who checks the control, and when?

1. Verify erection readiness

Hazard: Insufficient foundation strength or an unreported anchor modification can cause the column base to fail.

Control: Erection lead obtains the controlling contractor’s required written notifications and compares the foundation and anchor-rod arrangement with current documents. Resolve damaged, displaced or modified rods through the required engineering process; do not adapt the base in the field.

Verification: Lead records receipt and checks the identified column base before the lift proceeds.

Why this belongs in the analysis: A foundation that looks complete may still be unready for erection loads.

2. Establish receiving support and stability

Hazard: Incorrect leveling support or missing guys can allow a newly set column to overturn.

Control: Prepare the specified leveling plates, nuts or shim packs and approved anchorage. Have a competent person evaluate needed guying or bracing; arrange it and safe installer positions before hoisting rather than deciding under a suspended column.

Verification: Erection lead verifies support readiness and the competent-person stability determination.

Why this belongs in the analysis: The crane-release decision must be planned before the column arrives.

3. Inspect and rig the identified column

Hazard: Unsuitable gear or an incorrect member orientation can drop or swing the suspended column.

Control: Qualified rigging personnel match the member identity, weight, center of gravity and lift points to the planned lift and inspected gear. Keep workers clear of restrained stock and test the planned balance under the released lifting method.

Verification: Rigging lead checks member/gear compatibility and signal roles before the lift.

Why this belongs in the analysis: Similar-looking columns may need different lifting arrangements.

4. Hoist and receive from designated positions

Hazard: Workers can be caught between the moving column and base or struck in the suspended-load path.

Control: Maintain the planned hoisting exclusion and required signal control. Receive from designated positions using the planned alignment method with hands clear of closing base gaps; stop for unexpected movement or a lost boundary.

Verification: Lift lead checks the route and receiver positions through the controlled landing.

Why this belongs in the analysis: Hands and bodies cannot serve as stops for a crane-supported member.

5. Anchor and confirm initial stability

Hazard: Premature crane release can leave a column supported by incomplete or unsuitable anchorage.

Control: Install the released base and leveling arrangement and required anchorage; steel columns require at least four anchor rods under 1926.755. Complete needed guys/braces and the specified initial checks before the designated lead authorizes crane release.

Verification: Erection lead checks actual anchorage and installed temporary support against the release criteria.

Why this belongs in the analysis: The four-rod minimum does not replace the designed base and stability checks.

6. Release rigging and transfer restrictions

Hazard: Rigging removal or later brace interference can destabilize the column and expose other trades.

Control: After the designated crane-release decision, remove gear from protected access and maintain required temporary support. Communicate incomplete connections, loading limits and brace restrictions to the next erection operation; keep unapproved activity away.

Verification: Erection lead records initial stability handover and receiving crew responsibilities.

Why this belongs in the analysis: This column-set release does not authorize later support removal or arbitrary loading.

What does a useful control look like?

Needs improvementMore useful for this scenario
Bolt the column down and let the crane go.Erection lead verifies the released base arrangement, required anchorage and installed guys/braces before authorizing crane release.
The foundation is old enough.Lead receives the controlling contractor’s required written readiness notifications and resolves actual base discrepancies before erection.

Decisions that change the analysis

Do four anchor rods alone make the column ready for crane release?

No. The base/anchor assembly must meet its design requirements, and the competent-person evaluation determines required guys or braces. Fit, leveling support and installed stability arrangements remain part of the actual release decision.

What must the crew record for actual use?

Record the column identity, current erection/base design, required written notifications, competent-person guy/brace determination, actual support and anchorage findings, lift roles and crane-release decision. Keep later bolting, bay plumbing and brace-removal records separate.

Agree when the crew will pause

  • Missing foundation notification or unexpected anchor damage/modification.
  • The column does not seat on the released leveling/base arrangement.
  • Required guys/braces, controlled receiving positions or lift communication cannot be maintained.

After a pause, correct the condition, reassess the work, and obtain required authorization before restarting. Keep unresolved actions visible.

Download the worked example and free template

No account or paid membership required. The worked example contains planned controls. The blank template is for your own work; neither includes fabricated inspection results, signatures or approval.

Your editable working copy

Build and download your draft

Start blank or load the learning example. Replace its assumptions with your actual conditions and involve the people doing the work. Your entries stay in this browser tab; download a copy before leaving or refreshing.

1. Describe your work and site

2. Work through each task

Describe an observable step, how someone could be harmed, and the control that acts on that hazard. Identify who checks it and what evidence is needed.

Task 1

3. Record changes, checks, and open actions

Walk the work area, review with the crew, and resolve missing controls. Follow the required approval process. This tool does not judge completeness, verify signatures or authorize work.

Open the downloaded file in a browser, then use Print → Save as PDF for a printable copy.

Training needs to confirm

  • Steel erection training for assigned column-placement roles, including anchor/base recognition and initial stability hold points.
  • Qualified rigging/signal instruction as applicable, plus task-specific protected access, pinch-path and crane-release communication.

Confirm applicable qualifications, task instruction and actual training evidence for the people assigned. Related toolbox talks support crew discussion; they do not establish competence.

Common questions

Can this example be used as a JSA?

Adapt its Task | Hazard | Control analysis to the employer’s format and actual conditions. The example is a teaching aid, not evidence that controls were checked.

What changes if the project requires an AHA?

Use the governing AHA format, risk method, supporting records and acceptance process. The published formwork AHA demonstrates that additional structure; changing a JHA title does not supply it.

Are these resources part of a paid course?

This walkthrough, browser draft builder and downloads are free public resources, separate from Academy course enrollment.

References and source note

Original instructional scenario with planned controls. Primary references support hazard planning. Use actual equipment and product instructions, project design and employer requirements to establish field criteria. Use actual equipment instructions and site requirements alongside these references. Reference review: October 9, 2026.

Prepare the crew discussion

Related work activities