TPO Curb Flashing Installation JHA: Worked Example & Free Template

Plan tpo curb flashing installation with a defined worksite, six task steps, control verification, a worked example and editable templates.

By Todd Jerome Jenkins · Edition v1.0 · October 9, 2026

Get the example and template Build your draft

First, describe the work and worksite

A single-ply roofing crew will flash an accepted existing equipment curb on a released low-slope TPO roof. The work covers compatible curb upstands, corners, field welds and the specified top termination without setting equipment or altering the roof opening. This fictional learning example describes planned controls; it records no actual inspection or work authorization.

  • The curb and opening protection are accepted, with equipment isolation and nearby work coordination established where applicable.
  • The selected membrane system and actual curb geometry have an accepted compatible flashing and termination detail.
  • Equipment lifting, curb erection, opening enlargement, skylights and energized equipment servicing are excluded.

Questions before work

  • Which actual upstand, corner and termination detail applies to this curb?
  • How are the curb opening and nearby equipment hazards controlled?
  • What establishes acceptable weld conditions before final flashing begins?

Build the analysis one step at a time

What will the worker do? How could someone be harmed? What prevents or reduces that exposure? Who checks the control, and when?

1. Release curb access and nearby work

Hazard: An opening, active equipment or uncoordinated crew can expose the roofer around the curb.

Control: Confirm opening/edge protection, released roof access and coordination with the equipment owner. Resolve isolation and movement concerns before starting; maintain protection as the crew changes position around the curb.

Verification: Roofing lead records access, protection and equipment-interface findings.

Why this belongs in the analysis: An existing curb does not establish safe access or equipment status.

2. Confirm compatible materials and detail

Hazard: Wrong flashing materials or an unsuitable termination can leave defects that are hidden by subsequent work.

Control: Match membrane, accessories and substrate preparation to the accepted system detail and actual geometry. Stage only compatible materials within roof loading limits; stop where the existing curb or substrate cannot satisfy the released detail.

Verification: Lead confirms materials, curb condition and the actual detail revision.

Why this belongs in the analysis: A workable-looking corner is not evidence of a compatible system.

3. Establish tools and weld conditions

Hazard: Heat, electrical leads, wet conditions or unsuitable welding settings can expose workers and damage material.

Control: Inspect the suitable welding equipment and electrical protection, route leads clear of walking paths and keep combustibles controlled. Establish test-weld acceptance for the actual weather and material conditions under the system instructions before production work.

Verification: Assigned roofer records equipment checks and the required test-weld findings.

Why this belongs in the analysis: Settings from yesterday do not establish today’s acceptable weld.

4. Fit upstands and corners

Hazard: Cutting and awkward access can expose hands while poorly fitting corners create extra rework.

Control: Use controlled cuts and stable working positions to fit the specified flashing and corner components. Preserve required opening protection and geometry; avoid stretching or improvising material arrangements to bridge an unresolved fit or substrate defect.

Verification: Installer checks fit and corner detail before completing each assembly.

Why this belongs in the analysis: A fit problem can indicate a condition that the accepted detail does not cover.

5. Weld and finish termination

Hazard: Burns, missed corner seams or incomplete termination can occur at tight changes of plane.

Control: Maintain heat-tool control and the qualified welding conditions as the crew welds the required seams. Complete the specified curb-top termination, seal and fastening details, then inspect seams with the actual cooled-weld acceptance method; record defects for repair and recheck.

Verification: Roofing lead checks seam and termination findings, repairs and reinspection.

Why this belongs in the analysis: Three-dimensional corners need their own inspection rather than a field-seam assumption.

6. Hand over the flashed curb

Hazard: Unrecorded defects or access restrictions can expose the equipment or following roofing crew.

Control: Remove sharp scraps and secure tools. Record completed flashing, open repairs, protection and equipment-interface restrictions; transfer them to the receiving lead without implying that equipment operation or opening protection has been independently released.

Verification: Receiving lead acknowledges the flashing status and remaining actions.

Why this belongs in the analysis: Flashing completion does not authorize equipment use or removal of opening controls.

What does a useful control look like?

Needs improvementMore useful for this scenario
Work carefully and wear PPE.Inspect the suitable welding equipment and electrical protection, route leads clear of walking paths and keep combustibles controlled. Establish test-weld acceptance for the actual weather and material conditions under the system instructions before production work.
Check that everything is ready.Confirm opening/edge protection, released roof access and coordination with the equipment owner. Resolve isolation and movement concerns before starting; maintain protection as the crew changes position around the curb.

Decisions that change the analysis

Does a field-membrane test weld release every curb corner?

No. Establish suitable weld conditions, then inspect the actual flashing seams, corners and termination using the system criteria. Record defects, repairs and rechecks at this curb.

What must the crew record for actual use?

Identify the actual equipment and work boundaries, responsible people, applicable criteria, inspection findings and open actions. Resolve changes with affected crews and obtain required project authorization before work.

Agree when the crew will pause

  • Unaccepted curb/opening condition, equipment interface or incompatible materials.
  • Test welds or production seams fail the actual acceptance checks.
  • Wet/changed weather, defective equipment or a detail/fit change outside the released scope.

After a pause, correct the condition, reassess the work, and obtain required authorization before restarting. Keep unresolved actions visible.

Download the worked example and free template

No account or paid membership required. The worked example contains planned controls. The blank template is for your own work; neither includes fabricated inspection results, signatures or approval.

Your editable working copy

Build and download your draft

Start blank or load the learning example. Replace its assumptions with your actual conditions and involve the people doing the work. Your entries stay in this browser tab; download a copy before leaving or refreshing.

1. Describe your work and site

2. Work through each task

Describe an observable step, how someone could be harmed, and the control that acts on that hazard. Identify who checks it and what evidence is needed.

Task 1

3. Record changes, checks, and open actions

Walk the work area, review with the crew, and resolve missing controls. Follow the required approval process. This tool does not judge completeness, verify signatures or authorize work.

Open the downloaded file in a browser, then use Print → Save as PDF for a printable copy.

Training needs to confirm

  • TPO curb upstand/corner/termination detail, test welding and actual cooled-seam inspection instruction.
  • Heat-tool and electrical controls, opening/fall protection and equipment-owner coordination.

Confirm applicable qualifications, task instruction and actual training evidence for the people assigned. Related toolbox talks support crew discussion; they do not establish competence.

Common questions

Can this example be used as a JSA?

Adapt its Task | Hazard | Control analysis to the employer’s format and actual conditions. The example is a teaching aid, not evidence that controls were checked.

What changes if the project requires an AHA?

Use the governing AHA format, risk method, supporting records and acceptance process. The published formwork AHA demonstrates that additional structure; changing a JHA title does not supply it.

Are these resources part of a paid course?

This walkthrough, browser draft builder and downloads are free public resources, separate from Academy course enrollment.

References and source note

Original instructional scenario with planned controls. Primary references support hazard planning. Use actual equipment and product instructions, project design and employer requirements to establish field criteria. Use actual equipment instructions and site requirements alongside these references. Reference review: October 9, 2026.

Prepare the crew discussion