Hollow Masonry Adhesive Anchor Installation JHA
A JHA breaks the work into steps, hazards and controls. Use this example to build a draft for your actual job and review it with your crew.
Just need the example? Download it here.For the crew
You know the work. Let’s turn that experience into a plan your crew can talk through. Start with today’s job, then check the steps together.
Let’s build your JHA.
Step 1 of 4 · Working draft
Your job
Tell Jenkins what you’re planning and where the work will happen. Use the actual job details.
Use the published example’s suggestions when they fit your task, or write your own steps. These are planned controls, not verified worksite conditions.
Describe an observable step, how someone could be harmed, and the control that acts on that hazard. Identify who checks it and what evidence is needed.
Walk through the plan with the people doing the work. Resolve missing controls and agree who checks them. Moving to the next step does not approve the work.
Confirm people, equipment and emergency arrangements
Record changes, checks, and open actions
Walk the work area, review with the crew, and resolve missing controls. Follow the required approval process. This tool does not judge completeness, verify signatures or authorize work.
Print your own JHA by signing in, or contribute the selected structured categories as a guest. Signing in does not require research participation. Written job details are processed to prepare your export and are stored on our server only if you save to your private company library.
Research purpose, data fields, retention and withdrawal · Privacy notice
Sign-in uses a free account. Your tab draft is retained for the return from sign-in.
Hosted organization saving requires active jSMS access and a company workspace. View jSMS plans.
The export uses landscape pages, task-only continuation pages and a Page X of Y footer in current Chrome or Edge. Review every page. Opening an export is not proof that the JHA was printed or used. The PDF includes its research choice and reference; the private withdrawal link stays in the export’s screen-only receipt.
Device storage and other draft options
Device copies may contain private job information. Clear them when using a shared device.
Your entries stay in this working draft as you move between steps. Required field checks, employer review and work authorization remain separate.
Your Hollow Masonry Adhesive Anchor Installation JHA
Walk through the job in order. Use these possible hazards, planned controls and checks to start a conversation about your actual work.
011. Release substrate and anchor locations
Possible hazards: An anchor in an unsuitable cell, weak face shell or unidentified service can fail or cause contact injury.
Planned controls: Installation lead checks the identified masonry, service investigation and engineer’s anchor schedule against the product’s approved substrate range. Mark permitted locations and drilling limits; hold unknown units, damage or positions outside the released design.
Check before work: Lead records substrate identity and location release before drilling.
022. Arrange dust and chemical controls
Possible hazards: Drilling dust, adhesive contact and cluttered access can expose the installer and nearby workers.
Planned controls: Separate the work bay, prepare the system-approved drill and cleaning tools and establish the applicable silica controls. Stage labeled adhesive, sleeves and rods with current SDS, assessed protection, ventilation and washing access; contain dispensing waste.
Check before work: Lead checks the dust-control method and identified chemical handling arrangement.
033. Drill within the released method
Possible hazards: An unsuitable drill mode can damage the face shell or create an unapproved receiving hole.
Planned controls: Use the actual system’s permitted tool, drill mode and hole criteria with dust controls functioning. Stay within marked limits, control both affected faces where necessary and stop for unexpected void geometry, breakout or a concealed obstruction; do not enlarge the hole to fit another sleeve.
Check before work: Installer compares actual hole condition with the required system criteria.
044. Prepare the hole and sleeve
Possible hazards: An unclean hole or wrong screen can prevent the anchor system from forming its intended restraint.
Planned controls: Inspect and clean by the system’s approved method and fit the specified compatible screen sleeve. Assess exposure from cleaning and verify sleeve seating and condition; do not omit the sleeve, improvise a tube or copy a solid-concrete hole procedure.
Check before work: Installer records hole and sleeve findings before dispensing.
055. Inject and place the rod
Possible hazards: Unmixed adhesive, poor filling or movement during cure can leave an unsafe fastening.
Planned controls: Check product condition, dispenser and mixing nozzle, then follow the specified discard, dosing and rod-placement method within actual working limits. Protect the rod from movement and keep assessed contact protection in use; do not invent a common cure time.
Check before work: Installer records product identity, placement and conditions governing cure.
066. Isolate loading and hand over
Possible hazards: A fixture can be attached to an uncured or unaccepted anchor without the receiving crew knowing.
Planned controls: Mark unreleased anchors and prevent attachment or loading until the specified cure and acceptance are complete. Transfer actual installation records, required test findings and open actions to the designated reviewer; dispose of waste under the SDS and site arrangements.
Check before work: Receiving lead confirms the loading release or continuing restriction for each anchor.
Example scope and starting conditions
An installation crew will fit engineer-specified screened adhesive anchors through the face of an identified hollow-CMU wall at ground level for a later fixture. The accepted wall, permitted locations and actual anchor system govern drilling, installation and cure restrictions. This fictional learning example describes planned controls; it records no actual inspection or work authorization.
- The design and product approval identify the masonry unit, face/cell condition, sleeve, rod and required installation and acceptance criteria.
- The selected drilling and cleaning methods have task-specific dust controls; chemical handling follows the actual adhesive SDS.
- Core drilling, concrete starter bars, assumed solid substrate, facade tie repair and fixture loading before acceptance are excluded.
Know when to pause
- Masonry identity, face/cell condition or anchor location differs from the approved design.
- Breakout, failed dust control or an incompatible sleeve or cleaning tool.
- Product condition, cure requirements or the fixture-loading release is unresolved.
After a pause, correct the condition, reassess the work, and obtain required authorization before restarting.
Free example and template
No account required. The worked example contains planned controls. The blank template is for your own work; neither includes fabricated inspection results, signatures or approval.
Need help? Ask Jenkins
Jenkins · Your Safety Concierge
What brings you here today? Choose what you’re working on, or tell Jenkins about your situation.
Jenkins matches your words to published starting points. Keep names and private job details in your working draft. Suitable free resources come first.
For managers
Does the team have what it needs to carry out the plan? Give the crew time, equipment and support, and make it clear who will resolve anything that is missing.
Manager checks and supporting resources
Confirm the people doing the work have the time, equipment, information and support to carry out the plan. Agree who checks the controls and who resolves open actions.
Questions to resolve before work
- What evidence identifies the hollow masonry and permitted anchoring positions?
- Which sleeve, rod and drilling/cleaning method belong to the approved system?
- How will cure conditions, installation findings and the later fixture-loading release be recorded?
Training and qualifications to confirm
- The actual hollow-masonry anchor system’s approved substrate, drill mode, cleaning, sleeve, dispensing and cure procedure.
- Applicable silica and hazard-communication instruction, contact protection and installation-record/acceptance responsibilities.
Confirm the actual training evidence for the assigned people. A toolbox talk does not establish competence.
Decisions that change the plan
Can the installer omit a sleeve because the rod feels firm?
No. Follow the approved system for the identified hollow masonry. Firmness by hand is not an acceptance test, and this example supplies neither an anchor design nor permission to treat a hollow unit as solid concrete.
What must the crew record for actual use?
Identify the actual equipment and work boundaries, responsible people, applicable criteria, inspection findings and open actions. Resolve changes with affected crews and obtain required project authorization before work.
Keep planning connected
Resources that support this JHA
Additional tools for task planning and safe work. Start with the free resources; explore paid options only when they meet an additional need.
Toolbox talks for the work
Prepare a practical crew discussion.
Silica: Verify Dust Controls Before Cutting →Hazard Communication: Labels, SDS & the Task →Powered Tools: Check the Tool, Guard and Accessory →Safety program resources
Review procedures, roles, and requirements.
Browse the existing catalog and confirm the scope and purchase availability of each program.
Browse safety programs →Paid service · Availability
Task-specific training and qualifications
Explore applicable training and qualification needs.
Task-specific training services are not currently available to book here. Start with the free training-needs lookup; a toolbox talk or online course alone does not establish competence or employer authorization.
Review training needs · Free →People, equipment, emergency arrangements and open actions are recorded in the guided JHA’s Crew review step.
Open the crew review step →For safety professionals
How do we know the planning process and controls are working? Connect what the crew reports with field checks, risk decisions and the evidence behind your system.
Industry context, SIF, control verification and AHA review
Guidance and evidence
Review the method, risk decisions and evidence behind the plan. Use the actual jurisdiction, equipment instructions, employer process and project requirements.
Task-by-task control and verification rationale
1. Release substrate and anchor locations
Hazard: An anchor in an unsuitable cell, weak face shell or unidentified service can fail or cause contact injury.
Control: Installation lead checks the identified masonry, service investigation and engineer’s anchor schedule against the product’s approved substrate range. Mark permitted locations and drilling limits; hold unknown units, damage or positions outside the released design.
Verification: Lead records substrate identity and location release before drilling.
Why this belongs in the analysis: A hollow wall cannot be treated as a continuous concrete block.
2. Arrange dust and chemical controls
Hazard: Drilling dust, adhesive contact and cluttered access can expose the installer and nearby workers.
Control: Separate the work bay, prepare the system-approved drill and cleaning tools and establish the applicable silica controls. Stage labeled adhesive, sleeves and rods with current SDS, assessed protection, ventilation and washing access; contain dispensing waste.
Verification: Lead checks the dust-control method and identified chemical handling arrangement.
Why this belongs in the analysis: The sleeve installation combines material-specific drilling and chemical exposure.
3. Drill within the released method
Hazard: An unsuitable drill mode can damage the face shell or create an unapproved receiving hole.
Control: Use the actual system’s permitted tool, drill mode and hole criteria with dust controls functioning. Stay within marked limits, control both affected faces where necessary and stop for unexpected void geometry, breakout or a concealed obstruction; do not enlarge the hole to fit another sleeve.
Verification: Installer compares actual hole condition with the required system criteria.
Why this belongs in the analysis: Receiving-hole damage can undermine an otherwise correct adhesive installation.
4. Prepare the hole and sleeve
Hazard: An unclean hole or wrong screen can prevent the anchor system from forming its intended restraint.
Control: Inspect and clean by the system’s approved method and fit the specified compatible screen sleeve. Assess exposure from cleaning and verify sleeve seating and condition; do not omit the sleeve, improvise a tube or copy a solid-concrete hole procedure.
Verification: Installer records hole and sleeve findings before dispensing.
Why this belongs in the analysis: The hollow-substrate system relies on a controlled assembly around the receiving void.
5. Inject and place the rod
Hazard: Unmixed adhesive, poor filling or movement during cure can leave an unsafe fastening.
Control: Check product condition, dispenser and mixing nozzle, then follow the specified discard, dosing and rod-placement method within actual working limits. Protect the rod from movement and keep assessed contact protection in use; do not invent a common cure time.
Verification: Installer records product identity, placement and conditions governing cure.
Why this belongs in the analysis: The product and actual temperature conditions determine the installation window.
6. Isolate loading and hand over
Hazard: A fixture can be attached to an uncured or unaccepted anchor without the receiving crew knowing.
Control: Mark unreleased anchors and prevent attachment or loading until the specified cure and acceptance are complete. Transfer actual installation records, required test findings and open actions to the designated reviewer; dispose of waste under the SDS and site arrangements.
Verification: Receiving lead confirms the loading release or continuing restriction for each anchor.
Why this belongs in the analysis: A visible rod supplies no evidence of cure or tested capacity.
Compare control wording
| Needs improvement | More useful for this scenario |
|---|---|
| Work carefully and wear PPE. | Use the actual system’s permitted tool, drill mode and hole criteria with dust controls functioning. Stay within marked limits, control both affected faces where necessary and stop for unexpected void geometry, breakout or a concealed obstruction; do not enlarge the hole to fit another sleeve. |
| Check that everything is ready. | Installation lead checks the identified masonry, service investigation and engineer’s anchor schedule against the product’s approved substrate range. Mark permitted locations and drilling limits; hold unknown units, damage or positions outside the released design. |
Common questions
Can this example be used as a JSA?
Adapt its Task | Hazard | Control analysis to the employer’s format and actual conditions. The example is a teaching aid, not evidence that controls were checked.
What changes if the project requires an AHA?
Use the governing AHA format, risk method, supporting records and acceptance process. The published formwork AHA demonstrates that additional structure; changing a JHA title does not supply it.
Are these resources part of a paid course?
This walkthrough, browser draft builder and downloads are free public resources, separate from Academy course enrollment.
References and source note
- Hilti HIT-HY 270 Masonry adhesive anchor instructions and technical resources
- Hilti Hollow-CMU face anchorage and screened adhesive system clarification
- OSHA 1926.1153 Respirable crystalline silica
Original instructional scenario with planned controls. Primary references support hazard planning. Use actual equipment and product instructions, project design and employer requirements to establish field criteria. This example supplies no inspection findings or work authorization. Use actual equipment instructions and site requirements alongside these references. Reference review: October 9, 2026.
Developed by Todd Jerome Jenkins, MS, CSP · Edition v1.0 · October 13, 2026
Use the builder’s Print / Save as PDF action after signing in or accepting research participation.