Manufactured Roof Expansion-Joint Bellows Installation JHA
A JHA breaks the work into steps, hazards and controls. Use this example to build a draft for your actual job and review it with your crew.
Just need the example? Download it here.For the crew
You know the work. Let’s turn that experience into a plan your crew can talk through. Start with today’s job, then check the steps together.
Let’s build your JHA.
Step 1 of 4 · Working draft
Your job
Tell Jenkins what you’re planning and where the work will happen. Use the actual job details.
Use the published example’s suggestions when they fit your task, or write your own steps. These are planned controls, not verified worksite conditions.
Describe an observable step, how someone could be harmed, and the control that acts on that hazard. Identify who checks it and what evidence is needed.
Walk through the plan with the people doing the work. Resolve missing controls and agree who checks them. Moving to the next step does not approve the work.
Confirm people, equipment and emergency arrangements
Record changes, checks, and open actions
Walk the work area, review with the crew, and resolve missing controls. Follow the required approval process. This tool does not judge completeness, verify signatures or authorize work.
Print your own JHA by signing in, or contribute the selected structured categories as a guest. Signing in does not require research participation. Written job details are processed to prepare your export and are stored on our server only if you save to your private company library.
Research purpose, data fields, retention and withdrawal · Privacy notice
Sign-in uses a free account. Your tab draft is retained for the return from sign-in.
Hosted organization saving requires active jSMS access and a company workspace. View jSMS plans.
The export uses landscape pages, task-only continuation pages and a Page X of Y footer in current Chrome or Edge. Review every page. Opening an export is not proof that the JHA was printed or used. The PDF includes its research choice and reference; the private withdrawal link stays in the export’s screen-only receipt.
Device storage and other draft options
Device copies may contain private job information. Clear them when using a shared device.
Your entries stay in this working draft as you move between steps. Required field checks, employer review and work authorization remain separate.
Your Manufactured Roof Expansion-Joint Bellows Installation JHA
Walk through the job in order. Use these possible hazards, planned controls and checks to start a conversation about your actual work.
011. Accept the movement-joint detail and prepared supports
Possible hazards: An unsuitable bellows size, unaccepted curbs or a detail that blocks structural movement can fail and leave the roof opening or weather barrier compromised.
Planned controls: Lead matches the issued movement design, actual joint/curb geometry and accepted roofing interfaces to the identified Style CF assembly. Verify required factory transitions, section/splice parts, attachment and any size-dependent backing/support addendum. Resolve field differences with the designer and manufacturer before handling; do not adopt conceptual guide dimensions as an independent structural design.
Check before work: Technical lead records movement, supports and component acceptance.
022. Preserve independent opening protection and chemical controls
Possible hazards: A worker can fall into the joint or inhale primer/caulk vapor when installation changes a protected work position or exposes a low area.
Planned controls: Release safe access and independent opening/fall protection for both sides and transitions. Keep protection effective without stepping on bellows or backing foam. Verify current SDS for all selected mastic, primer and caulk; assess ventilation, ignition, skin/eye and respiratory controls, washing and waste before opening chemicals. Maintain protected storage and actual roof-load limits.
Check before work: Lead checks opening protection and chemical-control readiness.
033. Place factory intersections and transitions first
Possible hazards: Sharp flanges, awkward pieces or an incorrect starting transition can cut hands and force later sections into an unaccepted movement geometry.
Planned controls: Inspect the identified factory pieces and arrange controlled handling from protected positions. Install required factory intersections/transitions first under the applicable CF sequence and detail. Keep foam backing facing inward and protected from weather. Preserve specified movement/splice interfaces; do not field-fold a substitute transition or remove opening protection to obtain a convenient fit.
Check before work: Lead checks factory pieces, orientation and starting interfaces.
044. Attach straight sections one flange at a time
Possible hazards: Uncontrolled long sections, unsuitable mastic or extra fasteners can expose hands and restrict movement or create an inadequate curb attachment.
Planned controls: Retain each section during planned positioning and use the specified membrane-compatible mastic on the prepared receiving surfaces. Install one flange at a time with the actual accepted fastener arrangement, then continue the remaining sections while preserving prescribed end gaps. Keep independent protection intact. Stop for unaccepted substrate, strained fit or a proposed attachment change rather than forcing the bellows.
Check before work: Lead verifies flange attachment, gaps and unstrained geometry.
055. Prime and complete the prescribed splice tabs
Possible hazards: Unready primer, trapped corner gaps or incompatible caulk can leave a finished-looking discontinuity and expose workers to chemical contact.
Planned controls: Prepare and prime the specified flange/bellows splice area with compatible materials under actual instructions and SDS controls. Verify required primer readiness before placing the identified peel-and-stick tab. Work it into the prescribed corners and complete the actual tab-caulk treatment without stretching away movement or changing the gap. Check each splice while safe access and chemical separation remain effective.
Check before work: Installer records primer readiness, fit and splice findings.
066. Inspect weathering and transfer independent protection
Possible hazards: Hidden splice defects, weather-exposed foam or an incorrect cover assumption can harm following roof users and conceal unresolved movement or opening hazards.
Planned controls: Inspect the complete run, transitions, flange connections, splices and foam orientation against the accepted detail and actual instructions. Record defects and technical dispositions before weathering acceptance. Remove sharp scraps and collect chemical waste under the supplied SDS. Transfer continuing joint/access restrictions and independently maintained opening protection; completion gives no load-bearing, walkway or opening-cover credit.
Check before work: Receiving lead accepts weathering findings and continuing restrictions.
Example scope and starting conditions
A roofing crew will install specified JM Expand-O-Flash Style CF curb-to-curb bellows across an accepted structural movement joint. Released wood curbs and roofing receive factory transitions, straight sections and compatible splices while independent opening protection remains effective. This fictional example contains planned controls, without inspection findings or authorization.
- The designer accepts the actual movement range, bellows size, support/curb geometry, roofing interfaces and component/attachment schedule. Manufacturer CF instructions Rev 4, 09/09/2020, support the identified route and required size-dependent addendum; their conceptual drawings are not structural design acceptance.
- Smooth clean prepared curbs, protected work positions and permitted material loads are released before handling. Opening protection remains independent throughout installation and handover. Bellows, backing foam and metal flanges are neither a walking surface nor a load-rated opening cover.
- Roof flashing 238160-21 and low-slope roofing 238160-28 are partial connections: manufactured curb-to-curb movement-joint weathering only. New openings/curbs, roof-to-wall details, structural repair, ordinary sealant joints, field-made bellows, cover removal and movement-range changes are excluded.
Know when to pause
- Actual movement range, bellows size, curb geometry, support/addendum or roofing interface differs from the accepted detail.
- Independent opening protection, safe access, controlled handling or actual chemical/ignition/exposure arrangements cannot be maintained.
- Strained fit, unaccepted gaps, splice discontinuity, incompatible materials or weather-exposed foam requires a protected hold and technical resolution.
After a pause, correct the condition, reassess the work, and obtain required authorization before restarting.
Free example and template
No account required. The worked example contains planned controls. The blank template is for your own work; neither includes fabricated inspection results, signatures or approval.
Need help? Ask Jenkins
Jenkins · Your Safety Concierge
What brings you here today? Choose what you’re working on, or tell Jenkins about your situation.
Jenkins matches your words to published starting points. Keep names and private job details in your working draft. Suitable free resources come first.
For managers
Does the team have what it needs to carry out the plan? Give the crew time, equipment and support, and make it clear who will resolve anything that is missing.
Manager checks and supporting resources
Confirm the people doing the work have the time, equipment, information and support to carry out the plan. Agree who checks the controls and who resolves open actions.
Questions to resolve before work
- Who accepts the actual structural movement and selects the bellows, curb/attachment detail and required size-dependent support?
- How will independent opening protection remain effective while the crew works on both flanges and every transition?
- Which current compatible mastic, primer, splice tab and caulk instructions/SDS govern chemical handling and splice acceptance?
Training and qualifications to confirm
- Selected Style CF installation instruction for factory transitions, flange sequence, inward protected foam orientation, actual gaps/splice preparation and required support addendum, without field redesign.
- Crew instruction in independent opening/fall protection, sharp-flange and pinch control, actual chemical SDS/exposure arrangements, protected material handling and recording movement or substrate conflicts.
Confirm the actual training evidence for the assigned people. A toolbox talk does not establish competence.
Decisions that change the plan
What if the bellows cannot fit without restraining the joint?
Hold the affected installation and keep independent opening protection in place. Have the designer and manufacturer resolve actual movement, size, curb alignment and support. Do not stretch a section, add cross-joint fasteners, fill the structural gap or field-make a transition to hide the conflict. The correct weathering detail must accommodate the accepted movement before it is released.
What must the crew record for actual use?
Record joint/design and movement basis, curb/roofing interfaces, bellows/factory components, size addendum, attachment/splice instructions and actual chemical SDS/controls. Add opening protection, flange/gap/foam and splice findings, defects and technical disposition. Identify checkers and weathering/access handover; this example supplies no inspection or protection-removal release.
Keep planning connected
Resources that support this JHA
Additional tools for task planning and safe work. Start with the free resources; explore paid options only when they meet an additional need.
Toolbox talks for the work
Prepare a practical crew discussion.
Floor Holes: Before the Cover Comes Off →Solvent Vapors: Verify Airflow Before Opening →Roof Material Storage: Verify the Load Before Landing →Safety program resources
Review procedures, roles, and requirements.
Browse the existing catalog and confirm the scope and purchase availability of each program.
Browse safety programs →Paid service · Availability
Task-specific training and qualifications
Explore applicable training and qualification needs.
Task-specific training services are not currently available to book here. Start with the free training-needs lookup; a toolbox talk or online course alone does not establish competence or employer authorization.
Review training needs · Free →People, equipment, emergency arrangements and open actions are recorded in the guided JHA’s Crew review step.
Open the crew review step →For safety professionals
How do we know the planning process and controls are working? Connect what the crew reports with field checks, risk decisions and the evidence behind your system.
Industry context, SIF, control verification and AHA review
Guidance and evidence
Review the method, risk decisions and evidence behind the plan. Use the actual jurisdiction, equipment instructions, employer process and project requirements.
Task-by-task control and verification rationale
1. Accept the movement-joint detail and prepared supports
Hazard: An unsuitable bellows size, unaccepted curbs or a detail that blocks structural movement can fail and leave the roof opening or weather barrier compromised.
Control: Lead matches the issued movement design, actual joint/curb geometry and accepted roofing interfaces to the identified Style CF assembly. Verify required factory transitions, section/splice parts, attachment and any size-dependent backing/support addendum. Resolve field differences with the designer and manufacturer before handling; do not adopt conceptual guide dimensions as an independent structural design.
Verification: Technical lead records movement, supports and component acceptance.
Why this belongs in the analysis: The weathering detail must accommodate structural movement.
2. Preserve independent opening protection and chemical controls
Hazard: A worker can fall into the joint or inhale primer/caulk vapor when installation changes a protected work position or exposes a low area.
Control: Release safe access and independent opening/fall protection for both sides and transitions. Keep protection effective without stepping on bellows or backing foam. Verify current SDS for all selected mastic, primer and caulk; assess ventilation, ignition, skin/eye and respiratory controls, washing and waste before opening chemicals. Maintain protected storage and actual roof-load limits.
Verification: Lead checks opening protection and chemical-control readiness.
Why this belongs in the analysis: Weathering materials cannot replace fall or exposure controls.
3. Place factory intersections and transitions first
Hazard: Sharp flanges, awkward pieces or an incorrect starting transition can cut hands and force later sections into an unaccepted movement geometry.
Control: Inspect the identified factory pieces and arrange controlled handling from protected positions. Install required factory intersections/transitions first under the applicable CF sequence and detail. Keep foam backing facing inward and protected from weather. Preserve specified movement/splice interfaces; do not field-fold a substitute transition or remove opening protection to obtain a convenient fit.
Verification: Lead checks factory pieces, orientation and starting interfaces.
Why this belongs in the analysis: Factory pieces establish geometry for straight sections.
4. Attach straight sections one flange at a time
Hazard: Uncontrolled long sections, unsuitable mastic or extra fasteners can expose hands and restrict movement or create an inadequate curb attachment.
Control: Retain each section during planned positioning and use the specified membrane-compatible mastic on the prepared receiving surfaces. Install one flange at a time with the actual accepted fastener arrangement, then continue the remaining sections while preserving prescribed end gaps. Keep independent protection intact. Stop for unaccepted substrate, strained fit or a proposed attachment change rather than forcing the bellows.
Verification: Lead verifies flange attachment, gaps and unstrained geometry.
Why this belongs in the analysis: Secure attachment must preserve intended movement.
5. Prime and complete the prescribed splice tabs
Hazard: Unready primer, trapped corner gaps or incompatible caulk can leave a finished-looking discontinuity and expose workers to chemical contact.
Control: Prepare and prime the specified flange/bellows splice area with compatible materials under actual instructions and SDS controls. Verify required primer readiness before placing the identified peel-and-stick tab. Work it into the prescribed corners and complete the actual tab-caulk treatment without stretching away movement or changing the gap. Check each splice while safe access and chemical separation remain effective.
Verification: Installer records primer readiness, fit and splice findings.
Why this belongs in the analysis: A splice needs accepted preparation and corner fit.
6. Inspect weathering and transfer independent protection
Hazard: Hidden splice defects, weather-exposed foam or an incorrect cover assumption can harm following roof users and conceal unresolved movement or opening hazards.
Control: Inspect the complete run, transitions, flange connections, splices and foam orientation against the accepted detail and actual instructions. Record defects and technical dispositions before weathering acceptance. Remove sharp scraps and collect chemical waste under the supplied SDS. Transfer continuing joint/access restrictions and independently maintained opening protection; completion gives no load-bearing, walkway or opening-cover credit.
Verification: Receiving lead accepts weathering findings and continuing restrictions.
Why this belongs in the analysis: Weathering completion does not remove the opening hazard.
Compare control wording
| Needs improvement | More useful for this scenario |
|---|---|
| The new bellows covers the opening, so workers can cross it. | Separate accepted opening protection stays effective; bellows, backing foam and flanges receive no walking-surface or load-rated-cover credit. |
| Add fasteners or fill the gap until the joint looks sealed. | Follow accepted attachment, movement and splice geometry; any mismatch goes to the designer/manufacturer before the assembly is changed. |
Common questions
Can this example be used as a JSA?
Adapt the Task | Hazard | Control analysis to the employer’s JSA and actual work. Confirm assigned checks and record real findings before use.
What changes if the project requires an AHA?
Use the governing project format, risk method and acceptance process. The published formwork AHA illustrates additional structure; this example supplies no project risk rating or acceptance.
Are these resources part of a paid course?
This walkthrough, browser draft builder and downloads are free public resources, separate from Academy course enrollment.
References and source note
- JM Expand-O-Flash Style CF curb-to-curb instructions, Rev 4, 09/09/2020; actual size/addendum required
- JM current Style CF product page and compatible component documents
- JM low-VOC membrane primer SDS, 07/26/2019, current linked research document; match actual supply
- Expand-O-Flash tab caulking SDS, 05/12/2020, current linked research document; match actual supply
- OSHA 1926.501, opening/fall-protection and working-surface duties
Original instructional scenario with planned controls. Primary references support hazard planning. Use actual equipment and product instructions, project design and employer requirements to establish field criteria. This example supplies no inspection findings or work authorization. Use actual equipment instructions and site requirements alongside these references. Reference review: October 13, 2026.
Developed by Todd Jerome Jenkins, MS, CSP · Edition v1.0 · October 13, 2026