Walk Behind Concrete Floor Grinding JHA
A JHA breaks the work into steps, hazards and controls. Use this example to build a draft for your actual job and review it with your crew.
Just need the example? Download it here.For the crew
You know the work. Let’s turn that experience into a plan your crew can talk through. Start with today’s job, then check the steps together.
Let’s build your JHA.
Step 1 of 4 · Working draft
Your job
Tell Jenkins what you’re planning and where the work will happen. Use the actual job details.
Use the published example’s suggestions when they fit your task, or write your own steps. These are planned controls, not verified worksite conditions.
Describe an observable step, how someone could be harmed, and the control that acts on that hazard. Identify who checks it and what evidence is needed.
Walk through the plan with the people doing the work. Resolve missing controls and agree who checks them. Moving to the next step does not approve the work.
Confirm people, equipment and emergency arrangements
Record changes, checks, and open actions
Walk the work area, review with the crew, and resolve missing controls. Follow the required approval process. This tool does not judge completeness, verify signatures or authorize work.
Print your own JHA by signing in, or contribute the selected structured categories as a guest. Signing in does not require research participation. Written job details are processed to prepare your export and are stored on our server only if you save to your private company library.
Research purpose, data fields, retention and withdrawal · Privacy notice
Sign-in uses a free account. Your tab draft is retained for the return from sign-in.
Hosted organization saving requires active jSMS access and a company workspace. View jSMS plans.
The export uses landscape pages, task-only continuation pages and a Page X of Y footer in current Chrome or Edge. Review every page. Opening an export is not proof that the JHA was printed or used. The PDF includes its research choice and reference; the private withdrawal link stays in the export’s screen-only receipt.
Device storage and other draft options
Device copies may contain private job information. Clear them when using a shared device.
Your entries stay in this working draft as you move between steps. Required field checks, employer review and work authorization remain separate.
Your Walk Behind Concrete Floor Grinding JHA
Walk through the job in order. Use these possible hazards, planned controls and checks to start a conversation about your actual work.
011. Release the surface and removal limits
Possible hazards: Unknown coatings, embedded services or excessive removal can create hazardous exposure or damage the slab.
Planned controls: Surface lead identifies the released bare-concrete area, accepted nonstructural treatment and stop limits. Check available slab and material information and resolve uncertain areas with the responsible planner. Mark excluded locations and establish the receiving finish requirement without expanding the grinder operation into structural repair.
Check before work: Lead checks the work boundary and actual surface-treatment authorization with the operator.
022. Prepare the machine and work route
Possible hazards: An unstable machine, incompatible tooling or a trapped cable can cause unexpected movement, contact or electrical injury.
Planned controls: With the grinder disconnected, operator fits compatible tooling and checks guards, skirt, handles and controls under the actual manual. Prepare the specified electrical protection and sound cables. Clear the route and manage the extractor hose and power lead away from the grinding head, pinch areas and unrelated workers.
Check before work: Operator checks the isolated assembly, supply arrangement and manageable pass route before energizing.
033. Verify extraction and the silica-control method
Possible hazards: An apparently running extractor can leave respirable silica uncontrolled when airflow, filters or containment are unsuitable.
Planned controls: Assigned lead verifies the selected walk-behind floor-grinder method against the employer’s silica plan. Use manufacturer-recommended extraction with required airflow, filtration and filter cleaning; confirm sound connections and the specified function checks. Arrange indoor HEPA cleanup between passes and needed exhaust. Resolve additional assessed respiratory protection before work.
Check before work: Silica-control lead checks equipment specifications and actual function findings against the chosen method.
044. Make controlled surface-correction passes
Possible hazards: The rotating head, irregular floor or failed capture can injure nearby people or spread dust beyond the boundary.
Planned controls: Operator follows the selected manual and accepted removal method while maintaining stable footing and control of the machine. Keep others clear of the head and route; use the agreed pass sequence without forcing the grinder over excluded areas. Stop for unusual movement, damaged tooling, lost capture or an uncertain surface condition.
Check before work: Surface lead checks initial results and the operator verifies capture, route and boundaries during passes.
055. Isolate before tool checks and changes
Possible hazards: A restart, hot tooling or disturbed dust can injure the worker inspecting beneath the grinding head.
Planned controls: Stop and disconnect under the actual manual before accessing tooling or adjustment points. Use the specified stable servicing position and control stored movement; allow hot parts to cool as required. Maintain dust capture and assessed protection during tool changes, and replace only approved compatible parts before completing restart checks.
Check before work: Operator verifies disconnection and stable servicing support before anyone enters the head area.
066. Contain residue and hand over the surface
Possible hazards: Loose dust, overloaded collection bags or an unrecorded overgrind can expose the cleanup crew or mislead the next trade.
Planned controls: Use the silica plan’s HEPA collection and sealed handling method; avoid uncontrolled dry sweeping or dust-blowing cleanup. Disconnect and secure equipment after the final pass. Record actual surface results, excluded areas and defects for the receiving lead before later coatings, patching or polishing begin.
Check before work: Lead checks dust-contained cleanup and records the accepted boundary and unresolved surface findings.
Example scope and starting conditions
A trained operator will use an electric walk-behind planetary grinder for specified nonstructural correction on a bare, cured ground-floor slab. Accepted removal limits exclude structural depth and embedded services. Dry grinding uses manufacturer-recommended extraction and the employer’s floor-grinder silica method. Work ends with contained cleanup before coatings or polishing. This fictional learning example describes planned controls; it records no actual inspection or work authorization.
- The responsible planner has identified bare concrete and accepted the surface-treatment limits. Unknown coatings, hazardous contamination, embedded items or an uncertain removal depth are resolved before grinding; this resource does not authorize structural alteration.
- The actual grinder, tooling and extractor manuals govern compatibility, operating configuration, handling, electrical supply and tool changes. The employer fully implements the applicable walk-behind floor-grinder silica controls or establishes the required alternative exposure-control basis.
- Connections to repair and patching 238110-28 and placement and finishing 238110-09 are partial, limited to cured-floor surface correction. Handheld wall grinding, concrete placement, full polishing, coating removal and elevated or structural grinding are excluded.
Know when to pause
- Surface identity, coating status, embedded-item information or permitted removal depth becomes uncertain or differs from the accepted work.
- Extraction performance, a hose, filter, dust skirt or electrical protection cannot maintain the selected control method.
- The machine moves unexpectedly, tooling is damaged, the cable enters the danger area, or the route becomes unmanageable.
After a pause, correct the condition, reassess the work, and obtain required authorization before restarting.
Free example and template
No account required. The worked example contains planned controls. The blank template is for your own work; neither includes fabricated inspection results, signatures or approval.
Need help? Ask Jenkins
Jenkins · Your Safety Concierge
What brings you here today? Choose what you’re working on, or tell Jenkins about your situation.
Jenkins matches your words to published starting points. Keep names and private job details in your working draft. Suitable free resources come first.
For managers
Does the team have what it needs to carry out the plan? Give the crew time, equipment and support, and make it clear who will resolve anything that is missing.
Manager checks and supporting resources
Confirm the people doing the work have the time, equipment, information and support to carry out the plan. Agree who checks the controls and who resolves open actions.
Questions to resolve before work
- Who establishes the accepted surface-removal limits and confirms bare concrete without an unresolved coating or embedded-item concern?
- Which actual grinder and extractor combination meets the chosen floor-grinder silica-control method, including indoor between-pass cleanup?
- How will the machine, hose and power cable stay controlled during passes, isolation and tool changes?
Training and qualifications to confirm
- Selected-grinder instruction on tooling, guards, handling, stop controls and verified disconnection before servicing or tool changes.
- Floor-grinder silica-control instruction on extraction, filtration, containment and indoor HEPA cleanup between passes; recognize failure and follow the employer’s exposure/protection plan.
Confirm the actual training evidence for the assigned people. A toolbox talk does not establish competence.
Decisions that change the plan
Does the cosmetic wall-patching example already cover this work?
It uses localized handheld preparation before patching. This operation controls a traveling planetary floor machine, its cable and hose, tooling access and equipment-specific silica method across an accepted cured-floor area. It does not authorize deeper structural removal, unknown coating treatment or an entire polished-floor process.
What must the crew record for actual use?
Record the slab area and surface-treatment limits, bare-material basis, excluded locations, grinder/tooling and extractor identity, manual revisions, silica-control method and specification checks, electrical arrangement, operator assignment and actual findings. Record tool changes, control interruptions, cleanup and remaining defects for the receiving finish lead; this example provides no exposure measurement or surface acceptance.
Keep planning connected
Resources that support this JHA
Additional tools for task planning and safe work. Start with the free resources; explore paid options only when they meet an additional need.
Toolbox talks for the work
Prepare a practical crew discussion.
Silica: Verify Dust Controls Before Cutting →Electrical & Extension-Cord Checks →Energy Isolation: Verify Before Servicing →Safety program resources
Review procedures, roles, and requirements.
Browse the existing catalog and confirm the scope and purchase availability of each program.
Browse safety programs →Paid service · Availability
Task-specific training and qualifications
Explore applicable training and qualification needs.
Task-specific training services are not currently available to book here. Start with the free training-needs lookup; a toolbox talk or online course alone does not establish competence or employer authorization.
Review training needs · Free →People, equipment, emergency arrangements and open actions are recorded in the guided JHA’s Crew review step.
Open the crew review step →For safety professionals
How do we know the planning process and controls are working? Connect what the crew reports with field checks, risk decisions and the evidence behind your system.
Industry context, SIF, control verification and AHA review
Guidance and evidence
Review the method, risk decisions and evidence behind the plan. Use the actual jurisdiction, equipment instructions, employer process and project requirements.
Task-by-task control and verification rationale
1. Release the surface and removal limits
Hazard: Unknown coatings, embedded services or excessive removal can create hazardous exposure or damage the slab.
Control: Surface lead identifies the released bare-concrete area, accepted nonstructural treatment and stop limits. Check available slab and material information and resolve uncertain areas with the responsible planner. Mark excluded locations and establish the receiving finish requirement without expanding the grinder operation into structural repair.
Verification: Lead checks the work boundary and actual surface-treatment authorization with the operator.
Why this belongs in the analysis: A grinder can remove material beyond its permitted scope unless the boundary is made explicit.
2. Prepare the machine and work route
Hazard: An unstable machine, incompatible tooling or a trapped cable can cause unexpected movement, contact or electrical injury.
Control: With the grinder disconnected, operator fits compatible tooling and checks guards, skirt, handles and controls under the actual manual. Prepare the specified electrical protection and sound cables. Clear the route and manage the extractor hose and power lead away from the grinding head, pinch areas and unrelated workers.
Verification: Operator checks the isolated assembly, supply arrangement and manageable pass route before energizing.
Why this belongs in the analysis: Reliable machine control depends on both the tooling and the attached cables and hoses.
3. Verify extraction and the silica-control method
Hazard: An apparently running extractor can leave respirable silica uncontrolled when airflow, filters or containment are unsuitable.
Control: Assigned lead verifies the selected walk-behind floor-grinder method against the employer’s silica plan. Use manufacturer-recommended extraction with required airflow, filtration and filter cleaning; confirm sound connections and the specified function checks. Arrange indoor HEPA cleanup between passes and needed exhaust. Resolve additional assessed respiratory protection before work.
Verification: Silica-control lead checks equipment specifications and actual function findings against the chosen method.
Why this belongs in the analysis: Handheld-grinder rules and a spinning vacuum motor cannot establish compliance for this equipment category.
4. Make controlled surface-correction passes
Hazard: The rotating head, irregular floor or failed capture can injure nearby people or spread dust beyond the boundary.
Control: Operator follows the selected manual and accepted removal method while maintaining stable footing and control of the machine. Keep others clear of the head and route; use the agreed pass sequence without forcing the grinder over excluded areas. Stop for unusual movement, damaged tooling, lost capture or an uncertain surface condition.
Verification: Surface lead checks initial results and the operator verifies capture, route and boundaries during passes.
Why this belongs in the analysis: The next pass should remain within the accepted treatment instead of chasing an unexplained defect.
5. Isolate before tool checks and changes
Hazard: A restart, hot tooling or disturbed dust can injure the worker inspecting beneath the grinding head.
Control: Stop and disconnect under the actual manual before accessing tooling or adjustment points. Use the specified stable servicing position and control stored movement; allow hot parts to cool as required. Maintain dust capture and assessed protection during tool changes, and replace only approved compatible parts before completing restart checks.
Verification: Operator verifies disconnection and stable servicing support before anyone enters the head area.
Why this belongs in the analysis: An emergency-stop button alone is not the required disconnection before tooling work.
6. Contain residue and hand over the surface
Hazard: Loose dust, overloaded collection bags or an unrecorded overgrind can expose the cleanup crew or mislead the next trade.
Control: Use the silica plan’s HEPA collection and sealed handling method; avoid uncontrolled dry sweeping or dust-blowing cleanup. Disconnect and secure equipment after the final pass. Record actual surface results, excluded areas and defects for the receiving lead before later coatings, patching or polishing begin.
Verification: Lead checks dust-contained cleanup and records the accepted boundary and unresolved surface findings.
Why this belongs in the analysis: Clean appearance is separate from the agreed surface acceptance and control of collected dust.
Compare control wording
| Needs improvement | More useful for this scenario |
|---|---|
| Use the same dust setup as a handheld grinder. | Verify the actual walk-behind floor-grinder method, compatible extraction specifications and indoor HEPA cleanup requirements before passes. |
| Press stop and reach under the head. | Disconnect and establish the manual’s stable servicing condition, dust control and cooling requirements before touching tooling. |
Common questions
Can this example be used as a JSA?
Adapt its Task | Hazard | Control analysis to the employer’s JSA format and actual work. Confirm assigned checks and record real findings before relying on the plan.
What changes if the project requires an AHA?
Use the project’s governing AHA format, risk method, supporting records and acceptance process. The published formwork AHA illustrates that additional structure; this JHA establishes no AHA risk rating or acceptance.
Are these resources part of a paid course?
This walkthrough, browser draft builder and downloads are free public resources, separate from Academy course enrollment.
References and source note
- Husqvarna PG 5 and PG 5 S operator manual, current manufacturer download
- OSHA 1926.1153: walk-behind floor-grinder silica controls
- OSHA 1926.300 Tool condition and guarding
Original instructional scenario with planned controls. Primary references support hazard planning. Use actual equipment and product instructions, project design and employer requirements to establish field criteria. This example supplies no inspection findings or work authorization. Use actual equipment instructions and site requirements alongside these references. Reference review: October 9, 2026.
Developed by Todd Jerome Jenkins, MS, CSP · Edition v1.0 · October 13, 2026
Use the builder’s Print / Save as PDF action after signing in or accepting research participation.