Asphalt Shingle Roof Installation JHA
A JHA breaks the work into steps, hazards and controls. Use this example to build a draft for your actual job and review it with your crew.
Just need the example? Download it here.For the crew
You know the work. Let’s turn that experience into a plan your crew can talk through. Start with today’s job, then check the steps together.
Let’s build your JHA.
Step 1 of 4 · Working draft
Your job
Tell Jenkins what you’re planning and where the work will happen. Use the actual job details.
Use the published example’s suggestions when they fit your task, or write your own steps. These are planned controls, not verified worksite conditions.
Describe an observable step, how someone could be harmed, and the control that acts on that hazard. Identify who checks it and what evidence is needed.
Walk through the plan with the people doing the work. Resolve missing controls and agree who checks them. Moving to the next step does not approve the work.
Confirm people, equipment and emergency arrangements
Record changes, checks, and open actions
Walk the work area, review with the crew, and resolve missing controls. Follow the required approval process. This tool does not judge completeness, verify signatures or authorize work.
Print your own JHA by signing in, or contribute the selected structured categories as a guest. Signing in does not require research participation. Written job details are processed to prepare your export and are stored on our server only if you save to your private company library.
Research purpose, data fields, retention and withdrawal · Privacy notice
Sign-in uses a free account. Your tab draft is retained for the return from sign-in.
Hosted organization saving requires active jSMS access and a company workspace. View jSMS plans.
The export uses landscape pages, task-only continuation pages and a Page X of Y footer in current Chrome or Edge. Review every page. Opening an export is not proof that the JHA was printed or used. The PDF includes its research choice and reference; the private withdrawal link stays in the export’s screen-only receipt.
Device storage and other draft options
Device copies may contain private job information. Clear them when using a shared device.
Your entries stay in this working draft as you move between steps. Required field checks, employer review and work authorization remain separate.
Your Asphalt Shingle Roof Installation JHA
Walk through the job in order. Use these possible hazards, planned controls and checks to start a conversation about your actual work.
011. Release the pitched roof work area
Possible hazards: A weak deck or incomplete fall system can cause a fall or collapse.
Planned controls: Roofing lead confirms deck/underlayment handover and the selected fall-protection, access and rescue arrangements. Walk only the released protected route; correct exposed holes or unsuitable anchors before work.
Check before work: Lead checks the complete access-to-installation route.
022. Load and stage bundles
Possible hazards: Heavy bundles can overload the roof or slide onto workers below.
Planned controls: Use the planned hoisting/delivery method and permitted stack locations. Restrain stock for the slope and conditions, keep eaves clear and separate the ground drop zone.
Check before work: Material lead verifies load distribution and bundle stability.
033. Arrange work positions and tools
Possible hazards: Poor footing or hose routing can pull a worker off balance.
Planned controls: Use the selected protected work-position arrangement and tool instructions. Route hoses/cords away from travel and fall-system interference; never use an unapproved makeshift platform to compensate for the slope.
Check before work: Foreperson checks footing and tool/fall-system interfaces before fastening.
044. Lay and fasten shingles
Possible hazards: Fastening, sharp edges and awkward reaching can injure workers.
Planned controls: Follow product layout and fastening details from protected positions. Keep hands outside the nail path, use the actual nailer’s safe mode and controls, and advance material without reaching beyond stable footing.
Check before work: Installer checks tool operation and product fastening as work advances.
055. Complete transitions and ridge work
Possible hazards: Changing slope or reaching the ridge can defeat the earlier protection arrangement.
Planned controls: Reassess the protected position before ridge, hip or transition work. Use the system’s details and permitted access; hold any task that requires an unplanned anchor transfer or unprotected edge approach.
Check before work: Lead verifies protection for each changed work position.
066. Clear and hand over the roof
Possible hazards: Loose fasteners, offcuts or unsealed work can expose later crews.
Planned controls: Collect debris without sweeping it over the edge, secure remaining materials and communicate incomplete flashing or product sealing work. Leave required access/protection in place for the next task.
Check before work: Lead checks the roof and ground zone before release.
Example scope and starting conditions
A roofing crew will install asphalt shingles on a released pitched wood roof at a new low-rise building. The deck and underlayment are already prepared, and conventional fall protection and safe access are installed. This fictional learning example describes planned controls; it records no actual inspection or work authorization.
- The actual slope, surface, anchors and work-position arrangement are evaluated before roof access.
- Roof-load limits, shingle product instructions and fastening details govern staging and installation.
- Tear-off, deck repair, roof-truss work, safety-monitor-only methods and improvised toe boards are excluded.
Know when to pause
- Wet, icy, dusty or wind-affected surfaces impair control.
- Deck, loading or anchor/protection conditions differ from the release.
- Tool, material or ridge transition cannot be managed from protected positions.
After a pause, correct the condition, reassess the work, and obtain required authorization before restarting.
Free example and template
No account required. The worked example contains planned controls. The blank template is for your own work; neither includes fabricated inspection results, signatures or approval.
Need help? Ask Jenkins
Jenkins · Your Safety Concierge
What brings you here today? Choose what you’re working on, or tell Jenkins about your situation.
Jenkins matches your words to published starting points. Keep names and private job details in your working draft. Suitable free resources come first.
For managers
Does the team have what it needs to carry out the plan? Give the crew time, equipment and support, and make it clear who will resolve anything that is missing.
Manager checks and supporting resources
Confirm the people doing the work have the time, equipment, information and support to carry out the plan. Agree who checks the controls and who resolves open actions.
Questions to resolve before work
- Which fall system protects every access and installation position?
- How are shingle bundles loaded and restrained within roof limits?
- What surface or weather conditions require the crew to leave the roof?
Training and qualifications to confirm
- Applicable roof fall-protection training, anchor use and task-specific rescue planning.
- Shingle product, load staging and actual roofing nailer instruction.
Confirm the actual training evidence for the assigned people. A toolbox talk does not establish competence.
Decisions that change the plan
Does roof slope make a warning line sufficient for this job?
Do not apply low-slope roofing options to pitched/steep-slope work by assumption. Select the protection required for the actual slope and operation. This example uses conventional protection planned for every position.
What must the crew record for actual use?
Identify the actual equipment and work boundaries, responsible people, applicable criteria, inspection findings and open actions. Resolve changes with affected crews and obtain required project authorization before work.
Keep planning connected
Resources that support this JHA
Additional tools for task planning and safe work. Start with the free resources; explore paid options only when they meet an additional need.
Toolbox talks for the work
Prepare a practical crew discussion.
Fall Prevention: Verify the Controls →Manual Handling: Change the Lift Before You Lift →Powered Tools: Check the Tool, Guard and Accessory →Safety program resources
Review procedures, roles, and requirements.
Browse the existing catalog and confirm the scope and purchase availability of each program.
Browse safety programs →Paid service · Availability
Task-specific training and qualifications
Explore applicable training and qualification needs.
Task-specific training services are not currently available to book here. Start with the free training-needs lookup; a toolbox talk or online course alone does not establish competence or employer authorization.
Review training needs · Free →People, equipment, emergency arrangements and open actions are recorded in the guided JHA’s Crew review step.
Open the crew review step →For safety professionals
How do we know the planning process and controls are working? Connect what the crew reports with field checks, risk decisions and the evidence behind your system.
Industry context, SIF, control verification and AHA review
Guidance and evidence
Review the method, risk decisions and evidence behind the plan. Use the actual jurisdiction, equipment instructions, employer process and project requirements.
Task-by-task control and verification rationale
1. Release the pitched roof work area
Hazard: A weak deck or incomplete fall system can cause a fall or collapse.
Control: Roofing lead confirms deck/underlayment handover and the selected fall-protection, access and rescue arrangements. Walk only the released protected route; correct exposed holes or unsuitable anchors before work.
Verification: Lead checks the complete access-to-installation route.
Why this belongs in the analysis: Roof preparation and safe work access require separate evidence.
2. Load and stage bundles
Hazard: Heavy bundles can overload the roof or slide onto workers below.
Control: Use the planned hoisting/delivery method and permitted stack locations. Restrain stock for the slope and conditions, keep eaves clear and separate the ground drop zone.
Verification: Material lead verifies load distribution and bundle stability.
Why this belongs in the analysis: Roof slope changes the material’s storage behavior.
3. Arrange work positions and tools
Hazard: Poor footing or hose routing can pull a worker off balance.
Control: Use the selected protected work-position arrangement and tool instructions. Route hoses/cords away from travel and fall-system interference; never use an unapproved makeshift platform to compensate for the slope.
Verification: Foreperson checks footing and tool/fall-system interfaces before fastening.
Why this belongs in the analysis: The work position must accommodate the actual slope.
4. Lay and fasten shingles
Hazard: Fastening, sharp edges and awkward reaching can injure workers.
Control: Follow product layout and fastening details from protected positions. Keep hands outside the nail path, use the actual nailer’s safe mode and controls, and advance material without reaching beyond stable footing.
Verification: Installer checks tool operation and product fastening as work advances.
Why this belongs in the analysis: A fastening pattern does not replace nailer or fall controls.
5. Complete transitions and ridge work
Hazard: Changing slope or reaching the ridge can defeat the earlier protection arrangement.
Control: Reassess the protected position before ridge, hip or transition work. Use the system’s details and permitted access; hold any task that requires an unplanned anchor transfer or unprotected edge approach.
Verification: Lead verifies protection for each changed work position.
Why this belongs in the analysis: The final roof courses may create a different fall route.
6. Clear and hand over the roof
Hazard: Loose fasteners, offcuts or unsealed work can expose later crews.
Control: Collect debris without sweeping it over the edge, secure remaining materials and communicate incomplete flashing or product sealing work. Leave required access/protection in place for the next task.
Verification: Lead checks the roof and ground zone before release.
Why this belongs in the analysis: Cleanup must maintain the same roof and falling-object protection.
Compare control wording
| Needs improvement | More useful for this scenario |
|---|---|
| Work carefully and wear PPE. | Use the selected protected work-position arrangement and tool instructions. Route hoses/cords away from travel and fall-system interference; never use an unapproved makeshift platform to compensate for the slope. |
| Check that everything is ready. | Roofing lead confirms deck/underlayment handover and the selected fall-protection, access and rescue arrangements. Walk only the released protected route; correct exposed holes or unsuitable anchors before work. |
Common questions
Can this example be used as a JSA?
Adapt its Task | Hazard | Control analysis to the employer’s format and actual conditions. The example is a teaching aid, not evidence that controls were checked.
What changes if the project requires an AHA?
Use the governing AHA format, risk method, supporting records and acceptance process. The published formwork AHA demonstrates that additional structure; changing a JHA title does not supply it.
Are these resources part of a paid course?
This walkthrough, browser draft builder and downloads are free public resources, separate from Academy course enrollment.
References and source note
- OSHA 1926.501 Duty to have fall protection
- OSHA 1926.503 Fall protection training
- GAF Roof system installation resources
Original instructional scenario with planned controls. Primary references support hazard planning. Use actual equipment and product instructions, project design and employer requirements to establish field criteria. Use actual equipment instructions and site requirements alongside these references. Reference review: October 9, 2026.
Developed by Todd Jerome Jenkins, MS, CSP · Edition v1.0 · October 9, 2026