Cementitious Masonry Foundation Waterproofing JHA
A JHA breaks the work into steps, hazards and controls. Use this example to build a draft for your actual job and review it with your crew.
Just need the example? Download it here.For the crew
You know the work. Let’s turn that experience into a plan your crew can talk through. Start with today’s job, then check the steps together.
Let’s build your JHA.
Step 1 of 4 · Working draft
Your job
Tell Jenkins what you’re planning and where the work will happen. Use the actual job details.
Use the published example’s suggestions when they fit your task, or write your own steps. These are planned controls, not verified worksite conditions.
Describe an observable step, how someone could be harmed, and the control that acts on that hazard. Identify who checks it and what evidence is needed.
Walk through the plan with the people doing the work. Resolve missing controls and agree who checks them. Moving to the next step does not approve the work.
Confirm people, equipment and emergency arrangements
Record changes, checks, and open actions
Walk the work area, review with the crew, and resolve missing controls. Follow the required approval process. This tool does not judge completeness, verify signatures or authorize work.
Print your own JHA by signing in, or contribute the selected structured categories as a guest. Signing in does not require research participation. Written job details are processed to prepare your export and are stored on our server only if you save to your private company library.
Research purpose, data fields, retention and withdrawal · Privacy notice
Sign-in uses a free account. Your tab draft is retained for the return from sign-in.
Hosted organization saving requires active jSMS access and a company workspace. View jSMS plans.
The export uses landscape pages, task-only continuation pages and a Page X of Y footer in current Chrome or Edge. Review every page. Opening an export is not proof that the JHA was printed or used. The PDF includes its research choice and reference; the private withdrawal link stays in the export’s screen-only receipt.
Device storage and other draft options
Device copies may contain private job information. Clear them when using a shared device.
Your entries stay in this working draft as you move between steps. Required field checks, employer review and work authorization remain separate.
Your Cementitious Masonry Foundation Waterproofing JHA
Walk through the job in order. Use these possible hazards, planned controls and checks to start a conversation about your actual work.
011. Accept the foundation waterproofing interface
Possible hazards: Coating an unsound or actively leaking wall can conceal defects and fail without resolving the underlying water path.
Planned controls: Waterproofing lead matches the masonry survey and current detail to the selected product’s interior foundation application. Confirm accepted repairs, static/moving crack disposition, pressure-relief provisions and wall/floor transitions. Refer changed seepage or substrate conditions before work; a waterproof coating is not wall stabilization, drainage design or permission to drill relief holes.
Check before work: Lead records the actual substrate/interface release and resolved moisture-condition acceptance.
022. Prepare protected access and exposure controls
Possible hazards: Restricted reach, bag dust, wet cement and splash can expose the crew or contaminate surrounding areas.
Planned controls: Release floor/platform support and keep routes clear of stock and tools. Set a controlled mixing station with ventilation and assessed dry-material controls. Arrange product-specific hand, eye, clothing and respiratory measures where required, washing and spill response. Protect adjacent work and collect washwater; do not rely on an indoor wall’s appearance to settle exposure or access needs.
Check before work: Lead verifies stable access, mixing controls, washing and contained residue routes.
033. Verify and condition the prepared substrate
Possible hazards: Residual contamination, dry suction or an unaccepted void can prevent adhesion or hide a discontinuity.
Planned controls: Inspect the independently prepared wall against the actual system instructions. Hold contamination, loose material, active leakage or unresolved cracks for the responsible preparation/repair lead. Perform only the prescribed nonintrusive cleaning and water conditioning within this release, retaining controlled runoff. Verify the required surface state before coating; do not start powered preparation, cutting or additional patching under this example.
Check before work: Installer records prepared-wall findings and the instructed conditioning state.
044. Mix the identified compatible system
Possible hazards: Wrong liquid blend, dust release or contact with a rotating paddle can injure workers and compromise the coating.
Planned controls: Identify Thoroseal-581, Acryl 60 and permitted water against instructions/SDS. Measure the actual instructed blend and batch quantity; use the accepted slow-speed mixing-tool method with stable container support and hands clear. Follow prescribed wet-out/rest and remix requirements, isolating the tool before intervention. Add no substitute polymer or unscheduled water to rescue an aging batch.
Check before work: Operator records product identities, instructed batching and acceptable mixture condition.
055. Brush and inspect the prescribed coat sequence
Possible hazards: Pinholes, missed joints, poor timing or skin contact can leave an incomplete barrier and expose the applicator.
Planned controls: Apply by the accepted brush method, working material into the specified masonry surface while maintaining safe reach and cement protection. Verify coverage and discontinuities at the actual hold points. Follow the project/product criteria for subsequent coats and orientation; resolve differing masonry timing instructions with the manufacturer before continuation. Hold active water, adhesion failure or surface change rather than hiding it with extra material.
Check before work: Named checker records each coat’s actual coverage, condition and next-coat release.
066. Maintain cure protection and transfer status
Possible hazards: Early water exposure, later drilling or uncontrolled washing can damage the layer and mislead following trades.
Planned controls: Protect the completed coating through actual moisture, temperature and access requirements; assign continuing checks across shifts. Clean tools by the permitted wet method and contain cementitious washwater. Transfer coat records, cure observations and unresolved defects for designated acceptance. Preserve separately required relief/drainage measures; no generic curing period, dry-looking surface or product test rating establishes the foundation’s final waterproofing acceptance.
Check before work: Receiving lead verifies cure responsibility and remaining handover holds.
Example scope and starting conditions
A waterproofing crew will brush the selected Sika Thoroseal-581 and Acryl 60 system onto one released interior CMU foundation-wall area in an unoccupied building. The accepted floor and protected platform provide access without excavation entry. Required repairs, pressure-relief provisions and wall/floor interface preparation are independently complete. The operation controls substrate conditioning, material mixing, coat inspection and protected curing before the specified waterproofing handover. This fictional learning example describes planned controls; it records no actual inspection or work authorization.
- The current US waterproofing detail accepts the selected system, actual masonry and moisture/pressure condition. Wall soundness, active leakage, moving cracks, required relief and prepared transitions are technically resolved before coating.
- Current powder, modifier and mixing-tool instructions and SDS are available. Ventilation, dry-material exposure controls, washing, spill/washwater containment and accessible work positions are established.
- Foundation-construction coverage is partial: accepted masonry interior waterproof coating only. Wall laying, excavation, new weep drilling, active-leak plugging, structural repair, stucco, exterior backfilling and drainage redesign are excluded.
Know when to pause
- Current system/substrate acceptance, completed repairs, pressure disposition or interface readiness is missing.
- Dust/contact controls fail, active water appears, mixture identity changes or a coat has unacceptable adhesion or continuity.
- Cure protection cannot be maintained, next-coat criteria conflict or another trade proposes unaccepted drilling, covering or drainage changes.
After a pause, correct the condition, reassess the work, and obtain required authorization before restarting.
Free example and template
No account required. The worked example contains planned controls. The blank template is for your own work; neither includes fabricated inspection results, signatures or approval.
Need help? Ask Jenkins
Jenkins · Your Safety Concierge
What brings you here today? Choose what you’re working on, or tell Jenkins about your situation.
Jenkins matches your words to published starting points. Keep names and private job details in your working draft. Suitable free resources come first.
For managers
Does the team have what it needs to carry out the plan? Give the crew time, equipment and support, and make it clear who will resolve anything that is missing.
Manager checks and supporting resources
Confirm the people doing the work have the time, equipment, information and support to carry out the plan. Agree who checks the controls and who resolves open actions.
Questions to resolve before work
- What evidence accepts this coating for the actual wall and moisture/pressure condition?
- How will the selected modifier blend, prepared substrate and coat completeness be verified?
- Who retains responsibility for cure protection and the separate foundation/drainage acceptance?
Training and qualifications to confirm
- Selected cementitious waterproofing-system instruction covering substrate readiness, compatible powder/modifier, controlled mixing, coat inspection and cure protection.
- Dry-bag and wet-cement exposure prevention, safe paddle use, ventilation, contained washing and restricted-area handover.
Confirm the actual training evidence for the assigned people. A toolbox talk does not establish competence.
Decisions that change the plan
Is this a location variant of CMU laying or stucco?
CMU laying assembles units, reinforcement and temporary stability. The stucco example applies a specified finish coat to released lath. This work accepts a foundation moisture/pressure interface and constructs a continuous waterproof layer on retained masonry using the selected modifier, coating sequence and cure criteria. It does not claim complete foundation construction.
What must the crew record for actual use?
Record the actual work boundary, governing documents, responsible people, acceptance criteria, control findings and unresolved actions. Communicate restrictions and obtain required project authorization; this fictional example records no completed inspection or installed-control acceptance.
Keep planning connected
Resources that support this JHA
Additional tools for task planning and safe work. Start with the free resources; explore paid options only when they meet an additional need.
Toolbox talks for the work
Prepare a practical crew discussion.
Wet Concrete: Prevent Skin and Eye Contact →Hazard Communication: Labels, SDS & the Task →Silica: Verify Dust Controls Before Cutting →Safety program resources
Review procedures, roles, and requirements.
Browse the existing catalog and confirm the scope and purchase availability of each program.
Browse safety programs →Paid service · Availability
Task-specific training and qualifications
Explore applicable training and qualification needs.
Task-specific training services are not currently available to book here. Start with the free training-needs lookup; a toolbox talk or online course alone does not establish competence or employer authorization.
Review training needs · Free →People, equipment, emergency arrangements and open actions are recorded in the guided JHA’s Crew review step.
Open the crew review step →For safety professionals
How do we know the planning process and controls are working? Connect what the crew reports with field checks, risk decisions and the evidence behind your system.
Industry context, SIF, control verification and AHA review
Guidance and evidence
Review the method, risk decisions and evidence behind the plan. Use the actual jurisdiction, equipment instructions, employer process and project requirements.
Task-by-task control and verification rationale
1. Accept the foundation waterproofing interface
Hazard: Coating an unsound or actively leaking wall can conceal defects and fail without resolving the underlying water path.
Control: Waterproofing lead matches the masonry survey and current detail to the selected product’s interior foundation application. Confirm accepted repairs, static/moving crack disposition, pressure-relief provisions and wall/floor transitions. Refer changed seepage or substrate conditions before work; a waterproof coating is not wall stabilization, drainage design or permission to drill relief holes.
Verification: Lead records the actual substrate/interface release and resolved moisture-condition acceptance.
Why this belongs in the analysis: Surface treatment must follow an accepted water-management and substrate basis.
2. Prepare protected access and exposure controls
Hazard: Restricted reach, bag dust, wet cement and splash can expose the crew or contaminate surrounding areas.
Control: Release floor/platform support and keep routes clear of stock and tools. Set a controlled mixing station with ventilation and assessed dry-material controls. Arrange product-specific hand, eye, clothing and respiratory measures where required, washing and spill response. Protect adjacent work and collect washwater; do not rely on an indoor wall’s appearance to settle exposure or access needs.
Verification: Lead verifies stable access, mixing controls, washing and contained residue routes.
Why this belongs in the analysis: Readiness includes worker protection and waste handling.
3. Verify and condition the prepared substrate
Hazard: Residual contamination, dry suction or an unaccepted void can prevent adhesion or hide a discontinuity.
Control: Inspect the independently prepared wall against the actual system instructions. Hold contamination, loose material, active leakage or unresolved cracks for the responsible preparation/repair lead. Perform only the prescribed nonintrusive cleaning and water conditioning within this release, retaining controlled runoff. Verify the required surface state before coating; do not start powered preparation, cutting or additional patching under this example.
Verification: Installer records prepared-wall findings and the instructed conditioning state.
Why this belongs in the analysis: An apparently smooth surface does not demonstrate acceptable coating readiness.
4. Mix the identified compatible system
Hazard: Wrong liquid blend, dust release or contact with a rotating paddle can injure workers and compromise the coating.
Control: Identify Thoroseal-581, Acryl 60 and permitted water against instructions/SDS. Measure the actual instructed blend and batch quantity; use the accepted slow-speed mixing-tool method with stable container support and hands clear. Follow prescribed wet-out/rest and remix requirements, isolating the tool before intervention. Add no substitute polymer or unscheduled water to rescue an aging batch.
Verification: Operator records product identities, instructed batching and acceptable mixture condition.
Why this belongs in the analysis: The modifier and mixing process contribute to the selected system’s properties.
5. Brush and inspect the prescribed coat sequence
Hazard: Pinholes, missed joints, poor timing or skin contact can leave an incomplete barrier and expose the applicator.
Control: Apply by the accepted brush method, working material into the specified masonry surface while maintaining safe reach and cement protection. Verify coverage and discontinuities at the actual hold points. Follow the project/product criteria for subsequent coats and orientation; resolve differing masonry timing instructions with the manufacturer before continuation. Hold active water, adhesion failure or surface change rather than hiding it with extra material.
Verification: Named checker records each coat’s actual coverage, condition and next-coat release.
Why this belongs in the analysis: Uniform color does not demonstrate accepted waterproof continuity.
6. Maintain cure protection and transfer status
Hazard: Early water exposure, later drilling or uncontrolled washing can damage the layer and mislead following trades.
Control: Protect the completed coating through actual moisture, temperature and access requirements; assign continuing checks across shifts. Clean tools by the permitted wet method and contain cementitious washwater. Transfer coat records, cure observations and unresolved defects for designated acceptance. Preserve separately required relief/drainage measures; no generic curing period, dry-looking surface or product test rating establishes the foundation’s final waterproofing acceptance.
Verification: Receiving lead verifies cure responsibility and remaining handover holds.
Why this belongs in the analysis: Coating completion is one controlled stage within the foundation water-management system.
Compare control wording
| Needs improvement | More useful for this scenario |
|---|---|
| Brush cement paint over the wet wall. | Resolve wall soundness, leakage, pressure and transitions, then apply the accepted complete waterproofing system. |
| The surface looks dry; release the foundation. | Record coat and cure findings, retain protection and obtain the actual system acceptance with separate drainage responsibilities clear. |
Common questions
Can this example be used as a JSA?
Adapt the Task | Hazard | Control sequence to the employer’s JSA and actual worksite. Name control checkers and record findings; this fictional example supplies no completed inspection or authorization.
What changes if the project requires an AHA?
Use the governing AHA format, risk method, records and acceptance process. The published formwork AHA illustrates that structure. Add actual competencies, inspections and reviews; renaming a JHA does not complete them.
Are these resources part of a paid course?
This walkthrough, browser draft builder and downloads are free public resources, separate from Academy course enrollment.
References and source note
- Sika USA Thoroseal-581: masonry waterproofing instructions
- Sika Thoroseal-581 PDS, September 2024, version 02.01
- OSHA 1926.1153: construction silica exposure controls
Original instructional scenario with planned controls. Primary references support hazard planning. Use actual equipment and product instructions, project design and employer requirements to establish field criteria. This example supplies no inspection findings or work authorization. Use actual equipment instructions and site requirements alongside these references. Reference review: October 13, 2026.