Field Concrete Strength Specimen Production JHA
A JHA breaks the work into steps, hazards and controls. Use this example to build a draft for your actual job and review it with your crew.
Just need the example? Download it here.For the crew
You know the work. Let’s turn that experience into a plan your crew can talk through. Start with today’s job, then check the steps together.
Let’s build your JHA.
Step 1 of 4 · Working draft
Your job
Tell Jenkins what you’re planning and where the work will happen. Use the actual job details.
Use the published example’s suggestions when they fit your task, or write your own steps. These are planned controls, not verified worksite conditions.
Describe an observable step, how someone could be harmed, and the control that acts on that hazard. Identify who checks it and what evidence is needed.
Walk through the plan with the people doing the work. Resolve missing controls and agree who checks them. Moving to the next step does not approve the work.
Confirm people, equipment and emergency arrangements
Record changes, checks, and open actions
Walk the work area, review with the crew, and resolve missing controls. Follow the required approval process. This tool does not judge completeness, verify signatures or authorize work.
Print your own JHA by signing in, or contribute the selected structured categories as a guest. Signing in does not require research participation. Written job details are processed to prepare your export and are stored on our server only if you save to your private company library.
Research purpose, data fields, retention and withdrawal · Privacy notice
Sign-in uses a free account. Your tab draft is retained for the return from sign-in.
Hosted organization saving requires active jSMS access and a company workspace. View jSMS plans.
The export uses landscape pages, task-only continuation pages and a Page X of Y footer in current Chrome or Edge. Review every page. Opening an export is not proof that the JHA was printed or used. The PDF includes its research choice and reference; the private withdrawal link stays in the export’s screen-only receipt.
Device storage and other draft options
Device copies may contain private job information. Clear them when using a shared device.
Your entries stay in this working draft as you move between steps. Required field checks, employer review and work authorization remain separate.
Your Field Concrete Strength Specimen Production JHA
Walk through the job in order. Use these possible hazards, planned controls and checks to start a conversation about your actual work.
011. Establish specimen purpose and traceability
Possible hazards: A wrong sampling purpose or missing concrete identity can create a test set that is later applied to an unrelated pour or structural decision.
Planned controls: Testing lead obtains the actual plan, adopted method editions, qualified roles, specimen requirements and laboratory destination. Identify standard-cured acceptance specimens separately from other purposes and agree how each set links to delivery and placement records. Resolve an unclear sampling source before requesting concrete; the technician does not select release criteria or promise strength acceptance from this worked example.
Check before work: Lead confirms purpose, identities, applicable method and receiving laboratory before sampling.
022. Prepare safe sampling and initial-curing arrangements
Possible hazards: A technician entering the discharge path, an unstable workbench or unsuitable curing equipment can cause injury and compromise the specimens.
Planned controls: Coordinate the sampling position and command with the driver and placement lead, outside pinch, reversing and hose-movement paths. Prepare stable molds and work supports, clean washing and assessed cement-resistant protection. Check the actual initial-curing enclosure, monitoring and protected electrical supply where used. Do not take a sample until safe access and the required storage conditions can be maintained.
Check before work: Testing lead checks station, equipment, worker protection and the accepted sampling interface.
033. Obtain the representative sample through the agreed interface
Possible hazards: Uncoordinated collection can expose people to moving equipment and leave a selective sample that does not represent the intended delivery.
Planned controls: Qualified personnel collect and combine the required sample through the adopted method while the driver and placing team retain control of their equipment. Use manageable stable containers and keep skin and eyes protected from splashes. Record the actual source and sampling event, and hold deviations for the testing lead's disposition. Never climb onto or reach across active delivery equipment to recover missed material.
Check before work: Technician records required sample-source evidence and reports any sampling deviation.
044. Mold and identify the specified cylinders
Possible hazards: Wet concrete, unstable containers or incorrect consolidation can cause chemical exposure and produce specimens whose results are misleading.
Planned controls: At the prepared station, qualified technician molds, consolidates and finishes the specified cylinders through the actual adopted procedure with suitable equipment. Keep molds stable and hands protected, use the assessed electrical arrangement for any prescribed vibrator and avoid uncontrolled spills. Label each specimen through the agreed durable identification process. Hold a procedural or identity problem instead of silently making a replacement from unrelated leftover concrete.
Check before work: Technician records required molding findings, specimen identities and actual deviations.
055. Maintain and document initial curing
Possible hazards: Uncontrolled sunlight, freezing, disturbance or a missed shift can damage specimens while an apparently complete cylinder set hides the problem.
Planned controls: Place and protect the specimens through the actual initial-curing requirements and maintain the planned temperature/moisture controls and monitoring. Prevent unapproved movement and damage, keep power and access safe and transfer attendance between assigned personnel. Record real conditions and interruptions for the testing agency; do not invent readings or correct a curing deviation by relabeling the cylinders.
Check before work: Assigned custodian records actual curing observations, interruptions and responsibility handover.
066. Transfer identified specimens and unresolved findings
Possible hazards: Early or rough movement, moisture loss or broken custody can invalidate the test evidence and strain workers handling hardened specimens.
Planned controls: Testing lead obtains the actual method-based transfer readiness and uses protected containers and planned assistance for loading. Preserve required specimen conditions and identities through the accepted laboratory route. Send sampling, molding and initial-curing records with all deviations and obtain the receiving custody record. Keep test interpretation and concrete acceptance with their designated authorities; this handover records no test result or permission to load the slab.
Check before work: Receiving agency confirms set identity, condition history, custody and open issues.
Example scope and starting conditions
Qualified testing personnel will obtain a representative fresh-concrete sample during a separately controlled building slab placement and make identified standard-cured strength cylinders at a protected ground-level station. The actual sampling and specimen method govern preparation, initial curing and transfer to the testing agency. Specimen results and structural decisions remain separate. This fictional learning example describes planned controls and records no actual inspection or work authorization.
- The testing plan identifies the concrete, sample source, required adopted method editions, qualified personnel, specimen schedule and receiving laboratory. Actual mold, consolidation, initial-curing and transfer criteria are available; no universal specimen count, curing temperature or timing recipe is supplied.
- Truck and placing operations provide an accepted sampling interface without entry into a moving-equipment or discharge hazard. The protected station, suitable washing, curing enclosure and safe supply/transport arrangements are ready before a sample is requested.
- Placement/finishing 238110-09 and curing 238110-24 are partial connections: field production and initial curing of standard-cured acceptance specimens only. Delivery acceptance, slab curing, field-cured release specimens, maturity calibration, laboratory crushing and structural release are excluded.
Know when to pause
- Sampling purpose, concrete identity, adopted method, qualified personnel or receiving laboratory is unresolved.
- The safe collection interface, specimen preparation or required initial-curing conditions cannot be maintained.
- Identification, recorded curing history, specimen condition or transfer timing differs from the actual testing plan.
After a pause, correct the condition, reassess the work, and obtain required authorization before restarting.
Free example and template
No account required. The worked example contains planned controls. The blank template is for your own work; neither includes fabricated inspection results, signatures or approval.
Need help? Ask Jenkins
Jenkins · Your Safety Concierge
What brings you here today? Choose what you’re working on, or tell Jenkins about your situation.
Jenkins matches your words to published starting points. Keep names and private job details in your working draft. Suitable free resources come first.
For managers
Does the team have what it needs to carry out the plan? Give the crew time, equipment and support, and make it clear who will resolve anything that is missing.
Manager checks and supporting resources
Confirm the people doing the work have the time, equipment, information and support to carry out the plan. Agree who checks the controls and who resolves open actions.
Questions to resolve before work
- Which concrete delivery and placed location will these specimens represent under the actual sampling plan?
- Can the sampling and molding crew work outside moving truck, chute, hose and placement exposures?
- Who owns the required initial-curing conditions and documented transfer to the identified laboratory?
Training and qualifications to confirm
- Required concrete field-testing qualification and actual adopted sampling/specimen instruction, including mold preparation, consolidation, identification and curing records.
- Instruction on coordinated sampling access, wet-cement contact response, protected curing equipment, specimen handling and chain-of-custody discrepancy reporting.
Confirm the actual training evidence for the assigned people. A toolbox talk does not establish competence.
Decisions that change the plan
May a standard-cured acceptance set authorize form stripping by itself?
This example supplies no such authorization. Standard-cured acceptance specimens have a defined purpose under the testing plan. Any estimate of in-place strength or proposed support removal requires its actual accepted evidence and responsible release process. Do not relabel this set as field-cured or substitute its eventual result for a separate structural/load determination.
What must the testing crew record for actual use?
Record sample and represented-concrete identities, placement reference, required method and technician information, specimen labels, actual preparation findings and deviations. Preserve initial-curing observations, interruptions, custody, transport and laboratory receipt. Report limitations to the responsible testing/acceptance authority without prefilled readings, test strength, compliance or construction release.
Keep planning connected
Resources that support this JHA
Additional tools for task planning and safe work. Start with the free resources; explore paid options only when they meet an additional need.
Toolbox talks for the work
Prepare a practical crew discussion.
Wet Concrete: Prevent Skin and Eye Contact →Loading and Unloading: Who Releases the Vehicle? →Work Turnover: Transfer the State, Not Just the Story →Safety program resources
Review procedures, roles, and requirements.
Browse the existing catalog and confirm the scope and purchase availability of each program.
Browse safety programs →Paid service · Availability
Task-specific training and qualifications
Explore applicable training and qualification needs.
Task-specific training services are not currently available to book here. Start with the free training-needs lookup; a toolbox talk or online course alone does not establish competence or employer authorization.
Review training needs · Free →People, equipment, emergency arrangements and open actions are recorded in the guided JHA’s Crew review step.
Open the crew review step →For safety professionals
How do we know the planning process and controls are working? Connect what the crew reports with field checks, risk decisions and the evidence behind your system.
Industry context, SIF, control verification and AHA review
Guidance and evidence
Review the method, risk decisions and evidence behind the plan. Use the actual jurisdiction, equipment instructions, employer process and project requirements.
Task-by-task control and verification rationale
1. Establish specimen purpose and traceability
Hazard: A wrong sampling purpose or missing concrete identity can create a test set that is later applied to an unrelated pour or structural decision.
Control: Testing lead obtains the actual plan, adopted method editions, qualified roles, specimen requirements and laboratory destination. Identify standard-cured acceptance specimens separately from other purposes and agree how each set links to delivery and placement records. Resolve an unclear sampling source before requesting concrete; the technician does not select release criteria or promise strength acceptance from this worked example.
Verification: Lead confirms purpose, identities, applicable method and receiving laboratory before sampling.
Why this belongs in the analysis: Traceable specimens begin with an agreed question and an identified concrete population.
2. Prepare safe sampling and initial-curing arrangements
Hazard: A technician entering the discharge path, an unstable workbench or unsuitable curing equipment can cause injury and compromise the specimens.
Control: Coordinate the sampling position and command with the driver and placement lead, outside pinch, reversing and hose-movement paths. Prepare stable molds and work supports, clean washing and assessed cement-resistant protection. Check the actual initial-curing enclosure, monitoring and protected electrical supply where used. Do not take a sample until safe access and the required storage conditions can be maintained.
Verification: Testing lead checks station, equipment, worker protection and the accepted sampling interface.
Why this belongs in the analysis: A usable test plan needs a safe station and continuing curing capacity before fresh concrete arrives.
3. Obtain the representative sample through the agreed interface
Hazard: Uncoordinated collection can expose people to moving equipment and leave a selective sample that does not represent the intended delivery.
Control: Qualified personnel collect and combine the required sample through the adopted method while the driver and placing team retain control of their equipment. Use manageable stable containers and keep skin and eyes protected from splashes. Record the actual source and sampling event, and hold deviations for the testing lead's disposition. Never climb onto or reach across active delivery equipment to recover missed material.
Verification: Technician records required sample-source evidence and reports any sampling deviation.
Why this belongs in the analysis: Safe coordination and representative collection are both necessary for a meaningful specimen set.
4. Mold and identify the specified cylinders
Hazard: Wet concrete, unstable containers or incorrect consolidation can cause chemical exposure and produce specimens whose results are misleading.
Control: At the prepared station, qualified technician molds, consolidates and finishes the specified cylinders through the actual adopted procedure with suitable equipment. Keep molds stable and hands protected, use the assessed electrical arrangement for any prescribed vibrator and avoid uncontrolled spills. Label each specimen through the agreed durable identification process. Hold a procedural or identity problem instead of silently making a replacement from unrelated leftover concrete.
Verification: Technician records required molding findings, specimen identities and actual deviations.
Why this belongs in the analysis: The specimen must retain both its concrete identity and the prescribed preparation history.
5. Maintain and document initial curing
Hazard: Uncontrolled sunlight, freezing, disturbance or a missed shift can damage specimens while an apparently complete cylinder set hides the problem.
Control: Place and protect the specimens through the actual initial-curing requirements and maintain the planned temperature/moisture controls and monitoring. Prevent unapproved movement and damage, keep power and access safe and transfer attendance between assigned personnel. Record real conditions and interruptions for the testing agency; do not invent readings or correct a curing deviation by relabeling the cylinders.
Verification: Assigned custodian records actual curing observations, interruptions and responsibility handover.
Why this belongs in the analysis: Initial curing is part of specimen production, not a storage task that can be left unowned.
6. Transfer identified specimens and unresolved findings
Hazard: Early or rough movement, moisture loss or broken custody can invalidate the test evidence and strain workers handling hardened specimens.
Control: Testing lead obtains the actual method-based transfer readiness and uses protected containers and planned assistance for loading. Preserve required specimen conditions and identities through the accepted laboratory route. Send sampling, molding and initial-curing records with all deviations and obtain the receiving custody record. Keep test interpretation and concrete acceptance with their designated authorities; this handover records no test result or permission to load the slab.
Verification: Receiving agency confirms set identity, condition history, custody and open issues.
Why this belongs in the analysis: A laboratory needs the real specimen history to interpret the evidence responsibly.
Compare control wording
| Needs improvement | More useful for this scenario |
|---|---|
| Any leftover concrete can fill the cylinders. | Qualified personnel obtain and document the required representative sample from the identified delivery through the accepted interface. |
| The cylinders were left nearby, so their curing is complete. | Assign initial-curing ownership, maintain actual method requirements and send real conditions and deviations to the laboratory. |
Common questions
Can this example be adapted to a JSA?
Use its Task | Hazard | Control analysis in the employer's actual JSA format. Confirm the scenario, assigned verification and real findings before relying on the adapted work plan.
What changes when the project requires an AHA?
Apply the governing AHA format, risk method, supporting records and acceptance process. The published formwork AHA illustrates additional structure; this JHA supplies no completed AHA rating or acceptance.
Are these resources part of a paid course?
This walkthrough, browser draft builder and downloads are free public resources, separate from Academy course enrollment.
References and source note
- NRMCA CIP 34 Making Cylinders in the Field: preparation, curing and records
- NRMCA concrete materials FAQ: standard and field curing have different purposes
- OSHA 1926.404 Construction electrical wiring design and protection
Original instructional scenario with planned controls. Primary references support hazard planning. Use actual equipment and product instructions, project design and employer requirements to establish field criteria. This example supplies no inspection findings or work authorization. Use actual equipment instructions and site requirements alongside these references. Reference review: October 13, 2026.
Developed by Todd Jerome Jenkins, MS, CSP · Edition v1.0 · October 13, 2026