Mechanically Anchored Stone Cladding JHA
A JHA breaks the work into steps, hazards and controls. Use this example to build a draft for your actual job and review it with your crew.
Just need the example? Download it here.For the crew
You know the work. Let’s turn that experience into a plan your crew can talk through. Start with today’s job, then check the steps together.
Let’s build your JHA.
Step 1 of 4 · Working draft
Your job
Tell Jenkins what you’re planning and where the work will happen. Use the actual job details.
Use the published example’s suggestions when they fit your task, or write your own steps. These are planned controls, not verified worksite conditions.
Describe an observable step, how someone could be harmed, and the control that acts on that hazard. Identify who checks it and what evidence is needed.
Walk through the plan with the people doing the work. Resolve missing controls and agree who checks them. Moving to the next step does not approve the work.
Confirm people, equipment and emergency arrangements
Record changes, checks, and open actions
Walk the work area, review with the crew, and resolve missing controls. Follow the required approval process. This tool does not judge completeness, verify signatures or authorize work.
Print your own JHA by signing in, or contribute the selected structured categories as a guest. Signing in does not require research participation. Written job details are processed to prepare your export and are stored on our server only if you save to your private company library.
Research purpose, data fields, retention and withdrawal · Privacy notice
Sign-in uses a free account. Your tab draft is retained for the return from sign-in.
Hosted organization saving requires active jSMS access and a company workspace. View jSMS plans.
The export uses landscape pages, task-only continuation pages and a Page X of Y footer in current Chrome or Edge. Review every page. Opening an export is not proof that the JHA was printed or used. The PDF includes its research choice and reference; the private withdrawal link stays in the export’s screen-only receipt.
Device storage and other draft options
Device copies may contain private job information. Clear them when using a shared device.
Your entries stay in this working draft as you move between steps. Required field checks, employer review and work authorization remain separate.
Your Mechanically Anchored Stone Cladding JHA
Walk through the job in order. Use these possible hazards, planned controls and checks to start a conversation about your actual work.
011. Release the cladding detail
Possible hazards: An incompatible anchor or weak substrate can allow a panel to fall.
Planned controls: Stone lead verifies current engineered panel, bearing and anchor details and the substrate release. Refer uncertain edge distances, substrate damage or panel changes before drilling.
Check before work: Lead compares panel schedule and anchor locations with released documents.
022. Inspect and stage stone
Possible hazards: Cracked panels or unstable storage can fail during pickup.
Planned controls: Check panel identity, condition and specified handling points; segregate damaged stone for technical review. Stage on suitable restrained supports and maintain a clear transfer route.
Check before work: Handling lead inspects condition and support before attachment.
033. Prepare anchor points
Possible hazards: Drilling can strike services or expose workers to dust.
Planned controls: Investigate and release the drilling locations and depths. Use the specified anchor installation process and applicable dust controls; obtain required substrate/anchor checks without inventing acceptance values.
Check before work: Assigned installer records actual hole and anchor checks against the approved system.
044. Lift and position the panel
Possible hazards: Stone can drop, rotate or trap workers against the facade.
Planned controls: Use the rated stone-compatible handling system with inspected attachments and agreed signals. Keep people outside the drop and pinch paths; place the panel on its specified temporary bearing/support.
Check before work: Handling lead verifies support before the crew approaches connection work.
055. Complete mechanical restraint
Possible hazards: An incompletely connected panel can move when lifting support is released.
Planned controls: Install the specified anchors, bearings and required tolerances without forcing the stone. Retain handling/temporary support until designated connection checks and release are complete.
Check before work: Stone lead verifies each required support and restraint before disconnecting the device.
066. Hand over the facade
Possible hazards: Unfinished anchors or removed temporary supports can expose other trades.
Planned controls: Identify incomplete panels, remaining supports and loading/access restrictions. Clear the work zone and transfer inspection findings and open actions to the facade lead.
Check before work: Receiving lead confirms each panel’s release status.
Example scope and starting conditions
A specialist stone crew will install identified exterior granite cladding panels on a released ground-floor facade using specified mechanical anchors and a rated panel-handling device. This fictional learning example describes planned controls; it records no actual inspection or work authorization.
- Panel condition, anchor substrate, bearing and temporary support come from the engineered cladding details.
- Drilling occurs only at released anchor locations with the applicable dust controls.
- Adhered veneer, on-site stone fabrication, upper-story facade work and substituting adhesives for anchors are excluded.
Know when to pause
- Stone damage, unknown weight or incompatible handling device.
- Anchor substrate, drilling release or support differs from the design.
- Connection checks are unresolved or a temporary support change is proposed.
After a pause, correct the condition, reassess the work, and obtain required authorization before restarting.
Free example and template
No account required. The worked example contains planned controls. The blank template is for your own work; neither includes fabricated inspection results, signatures or approval.
Need help? Ask Jenkins
Jenkins · Your Safety Concierge
What brings you here today? Choose what you’re working on, or tell Jenkins about your situation.
Jenkins matches your words to published starting points. Keep names and private job details in your working draft. Suitable free resources come first.
For managers
Does the team have what it needs to carry out the plan? Give the crew time, equipment and support, and make it clear who will resolve anything that is missing.
Manager checks and supporting resources
Confirm the people doing the work have the time, equipment, information and support to carry out the plan. Agree who checks the controls and who resolves open actions.
Questions to resolve before work
- Which anchors and substrate checks establish this panel’s load path?
- What lifting device is approved for the stone surface and panel weight?
- Which temporary supports remain until the connection checks are complete?
Training and qualifications to confirm
- Stone-specific handling-device and anchorage installation instruction.
- Applicable rigging/handling qualifications and silica controls for actual anchor drilling.
Confirm the actual training evidence for the assigned people. A toolbox talk does not establish competence.
Decisions that change the plan
Can the adhered veneer mortar method replace an anchor?
No. Mechanically anchored dimension stone has an engineered load path. Any change in panel, anchor, bearing or attachment needs the responsible designer’s review; adhesive veneer instructions are not a substitute.
What must the crew record for actual use?
Identify the actual equipment and work boundaries, responsible people, applicable criteria, inspection findings and open actions. Resolve changes with affected crews and obtain required project authorization before work.
Keep planning connected
Resources that support this JHA
Additional tools for task planning and safe work. Start with the free resources; explore paid options only when they meet an additional need.
Toolbox talks for the work
Prepare a practical crew discussion.
Rigging: Before the Load Moves →Silica: Verify Dust Controls Before Cutting →Line of Fire: Swing Radius & Suspended Loads →Safety program resources
Review procedures, roles, and requirements.
Browse the existing catalog and confirm the scope and purchase availability of each program.
Browse safety programs →Paid service · Availability
Task-specific training and qualifications
Explore applicable training and qualification needs.
Task-specific training services are not currently available to book here. Start with the free training-needs lookup; a toolbox talk or online course alone does not establish competence or employer authorization.
Review training needs · Free →People, equipment, emergency arrangements and open actions are recorded in the guided JHA’s Crew review step.
Open the crew review step →For safety professionals
How do we know the planning process and controls are working? Connect what the crew reports with field checks, risk decisions and the evidence behind your system.
Industry context, SIF, control verification and AHA review
Guidance and evidence
Review the method, risk decisions and evidence behind the plan. Use the actual jurisdiction, equipment instructions, employer process and project requirements.
Task-by-task control and verification rationale
1. Release the cladding detail
Hazard: An incompatible anchor or weak substrate can allow a panel to fall.
Control: Stone lead verifies current engineered panel, bearing and anchor details and the substrate release. Refer uncertain edge distances, substrate damage or panel changes before drilling.
Verification: Lead compares panel schedule and anchor locations with released documents.
Why this belongs in the analysis: A finish-panel location does not establish its support capacity.
2. Inspect and stage stone
Hazard: Cracked panels or unstable storage can fail during pickup.
Control: Check panel identity, condition and specified handling points; segregate damaged stone for technical review. Stage on suitable restrained supports and maintain a clear transfer route.
Verification: Handling lead inspects condition and support before attachment.
Why this belongs in the analysis: Natural stone condition affects both handling and anchorage.
3. Prepare anchor points
Hazard: Drilling can strike services or expose workers to dust.
Control: Investigate and release the drilling locations and depths. Use the specified anchor installation process and applicable dust controls; obtain required substrate/anchor checks without inventing acceptance values.
Verification: Assigned installer records actual hole and anchor checks against the approved system.
Why this belongs in the analysis: Anchor preparation is part of the permanent load path.
4. Lift and position the panel
Hazard: Stone can drop, rotate or trap workers against the facade.
Control: Use the rated stone-compatible handling system with inspected attachments and agreed signals. Keep people outside the drop and pinch paths; place the panel on its specified temporary bearing/support.
Verification: Handling lead verifies support before the crew approaches connection work.
Why this belongs in the analysis: A glass handling device is not automatically suitable for stone.
5. Complete mechanical restraint
Hazard: An incompletely connected panel can move when lifting support is released.
Control: Install the specified anchors, bearings and required tolerances without forcing the stone. Retain handling/temporary support until designated connection checks and release are complete.
Verification: Stone lead verifies each required support and restraint before disconnecting the device.
Why this belongs in the analysis: Apparent alignment does not prove the panel is safely restrained.
6. Hand over the facade
Hazard: Unfinished anchors or removed temporary supports can expose other trades.
Control: Identify incomplete panels, remaining supports and loading/access restrictions. Clear the work zone and transfer inspection findings and open actions to the facade lead.
Verification: Receiving lead confirms each panel’s release status.
Why this belongs in the analysis: The handover must follow individual connection status, not visual finish.
Compare control wording
| Needs improvement | More useful for this scenario |
|---|---|
| Work carefully and wear PPE. | Investigate and release the drilling locations and depths. Use the specified anchor installation process and applicable dust controls; obtain required substrate/anchor checks without inventing acceptance values. |
| Check that everything is ready. | Stone lead verifies current engineered panel, bearing and anchor details and the substrate release. Refer uncertain edge distances, substrate damage or panel changes before drilling. |
Common questions
Can this example be used as a JSA?
Adapt its Task | Hazard | Control analysis to the employer’s format and actual conditions. The example is a teaching aid, not evidence that controls were checked.
What changes if the project requires an AHA?
Use the governing AHA format, risk method, supporting records and acceptance process. The published formwork AHA demonstrates that additional structure; changing a JHA title does not supply it.
Are these resources part of a paid course?
This walkthrough, browser draft builder and downloads are free public resources, separate from Academy course enrollment.
References and source note
- Natural Stone Institute Anchorage technical bulletins
- OSHA 1926.1153 Respirable crystalline silica
- OSHA 1926.21 Safety training and education
Original instructional scenario with planned controls. Primary references support hazard planning. Use actual equipment and product instructions, project design and employer requirements to establish field criteria. Use actual equipment instructions and site requirements alongside these references. Reference review: October 9, 2026.