Download the free toolbox talk
The one-page talk, editable Word version, and guidance below are open to everyone. No account required.
One-page toolbox talk
Download one-page toolbox talk (PDF, 1 page)Editable one-page toolbox talk (Word)Preview the one-page toolbox talk

Supporting documents
Included with free Safety & Systems membership.
Supervisor field check
A separate check to verify conditions and controls before work. Includes a one-page PDF and editable Word file.
Attendance sheet
A separate sign-in sheet to record the crew discussion. Includes a one-page PDF and editable Word file.
Need the crew records? Join free to use these supporting documents and the Safety & Systems Academy. No payment details. Email updates are optional.
Get supporting documents — free membershipAlready a member? Use the same link to sign in.
Hazard-based toolbox talk 5 of 52, with a practical HOP exercise.
Plan a 5–10 minute toolbox discussion, plus time to verify the actual controls. The one-page toolbox talk and editable Word version are public. Separate supervisor and attendance records are included with free Safety & Systems membership.
Why this matters
Moving a tool to another outlet changes its supply. The tool running at the previous location does not prove protection at the next one.
Learning objective
Confirm the actual point-of-use protection before reconnecting.
Key hazards or failure points
Unknown supply; assumed GFCI protection; untraceable grounding tests; damaged leads; wet connections; repeated resetting after a trip.
Practical controls
- Follow the employer’s compliant construction ground-fault protection arrangement. Workers must not informally substitute an assured grounding program for GFCI protection.
- Keep defective cords and equipment out of use. Have authorized electrical personnel resolve supply or equipment defects.
- Protect leads and connections from water, traffic and damage under equipment instructions and the site arrangement; reassess every supply change.
Verify It in the Field
- Identify the actual outlet and protection with the responsible electrical person. A nearby protective device does not prove this outlet is covered.
- For GFCI protection, use the specified safe manufacturer check. Under an assured grounding program, confirm applicable inspection and traceable current test evidence.
- Inspect accessible disconnected equipment under the procedure and review the new route. Record supply identification, evidence, verifier and time before use.
Stop and reassess
Hold use for unknown protection, failed testing, damage, unsuitable moisture exposure or repeated trips. Keep clear and obtain electrical help; do not bypass protection, open enclosures or probe circuits.
Crew discussion questions
- Which device or program protects this outlet?
- What evidence follows the equipment to this location?
- Who resolves a failed test or repeated trip?
For each required control, record its acceptance source and criterion, safe verification method, responsible verifier, actual result and time. Mark VERIFIED, HOLD/NOT VERIFIED, or N/A with a reason. Complete all required inspections; never enter danger or improvise a test to fill out a form.
Use this HOP tool
Validate assumptions
State the assumption: this new outlet has the protection our task needs. Name the evidence that would establish it and the person authorized to verify it. Keep the tool disconnected until the responsible person resolves the uncertainty under the site procedure.
This exercise supports hazard identification or control verification. It does not replace safeguards, required training, specialist decisions or work authorization.
Leader preparation and practical detail
Match evidence to the new outlet
Illustrative situation: a crew moves an extension lead because its original outlet is needed by another trade. Before reconnection, establish the new supply’s protective arrangement. A label on the tool or successful operation at the previous outlet does not establish protection here.
Respect the two construction arrangements
1926.404(b)(1) permits the specified GFCI arrangement or a compliant assured equipment grounding conductor program within its scope. The latter requires a written program, designated competent person, inspections, tests and records. It is not an informal choice made by a tool user. Apply exceptions and any stricter site requirements through the employer’s electrical process.
Verify without electrical exposure
Use actual manufacturer instructions for GFCI checks and the employer’s prescribed method and authorized roles. Required grounding tests belong to people competent and authorized to perform them. Do not create a fault, use an improvised tester or open energized equipment. Worn cords remain prohibited under 1926.416(e); a successful protective-device check does not repair a damaged lead.
Short supervisor field check
- Supply point identified
- Applicable protection confirmed
- Required test evidence
- Equipment and route sound
- Change communicated
Use the separate sheet to document evidence, unresolved restrictions, correction owner, recheck and required release authority. Rebrief affected workers. This record does not replace specialist inspections, permits or engineering determinations.
Attendance and follow-through
Use the separate attendance record for participants, roles, questions, actions and late-arrival rebriefs. Attendance does not prove competence, functioning controls or authorization. Keep completed records private under employer procedures.
Source acknowledgment
HOP concepts are adapted from DOE-HDBK-1028-2009, Human Performance Improvement Handbook, Volume 2 (June 2009). Todd Jerome Jenkins makes no claim to authorship or copyright ownership of original U.S. Government work. The explanations and exercises are original adaptations; no endorsement by DOE or the U.S. Government is implied. Third-party material credited in the handbook retains its separate ownership.
HOP source: Volume 2/VOLUME 2 VALIDATE ASSUMPTIONS.pdf; Printed pp. 22–23. The handbook supplies concepts; task-specific technical references are listed below.
Technical scope and references
Technical sources inspected October 9, 2026; resource edition October 12, 2026. Apply current jurisdictional requirements, the actual task procedure, manufacturer instructions, permits and required competent or qualified decisions. This resource supplies no equipment-specific acceptance criteria.
- OSHA 29 CFR 1926.404 — (b)(1): construction GFCI and assured equipment grounding conductor program, including its scope and exceptions.
- OSHA 29 CFR 1926.416 — (b)(2),(e): cord routing and prohibited damaged cords/attachments.
- DOE-HDBK-1028-2009 Volume 2 — Validate assumptions — Printed pp. 22–23; historical HOP tool basis, adapted exercise.
Connect this discussion to your JHA/JSA
Use the JHA/JSA planning and field-verification worksheet to connect this discussion to the actual task, controls and responsible people.
Related Todd Jerome Jenkins articles: How to Conduct a Job Safety Analysis and What Is Human and Organizational Performance?.
Related toolbox talks
- Electrical & Extension-Cord Checks
- Electrical Work: Verify the Boundary
- Assumptions: Show What Is Known and What Is Not
Continue the hazard series
Put one verification into practice
Record today’s change and evidence using the free JHA/JSA planning and field-verification worksheet.