Anchored Brick Veneer Construction JHA
A JHA breaks the work into steps, hazards and controls. Use this example to build a draft for your actual job and review it with your crew.
Just need the example? Download it here.For the crew
You know the work. Let’s turn that experience into a plan your crew can talk through. Start with today’s job, then check the steps together.
Let’s build your JHA.
Step 1 of 4 · Working draft
Your job
Tell Jenkins what you’re planning and where the work will happen. Use the actual job details.
Use the published example’s suggestions when they fit your task, or write your own steps. These are planned controls, not verified worksite conditions.
Describe an observable step, how someone could be harmed, and the control that acts on that hazard. Identify who checks it and what evidence is needed.
Walk through the plan with the people doing the work. Resolve missing controls and agree who checks them. Moving to the next step does not approve the work.
Confirm people, equipment and emergency arrangements
Record changes, checks, and open actions
Walk the work area, review with the crew, and resolve missing controls. Follow the required approval process. This tool does not judge completeness, verify signatures or authorize work.
Print your own JHA by signing in, or contribute the selected structured categories as a guest. Signing in does not require research participation. Written job details are processed to prepare your export and are stored on our server only if you save to your private company library.
Research purpose, data fields, retention and withdrawal · Privacy notice
Sign-in uses a free account. Your tab draft is retained for the return from sign-in.
Hosted organization saving requires active jSMS access and a company workspace. View jSMS plans.
The export uses landscape pages, task-only continuation pages and a Page X of Y footer in current Chrome or Edge. Review every page. Opening an export is not proof that the JHA was printed or used. The PDF includes its research choice and reference; the private withdrawal link stays in the export’s screen-only receipt.
Device storage and other draft options
Device copies may contain private job information. Clear them when using a shared device.
Your entries stay in this working draft as you move between steps. Required field checks, employer review and work authorization remain separate.
Your Anchored Brick Veneer Construction JHA
Walk through the job in order. Use these possible hazards, planned controls and checks to start a conversation about your actual work.
011. Accept support and backing
Possible hazards: An inadequate ledge or unready backing can leave the veneer without its intended load path.
Planned controls: Masonry lead checks the ledge, completed backing and current veneer details with the responsible framing or facade lead. Establish the applicable masonry access restriction and temporary stability arrangements; hold construction where support or anchorage is unresolved.
Check before work: Lead records the receiving-interface release before laying the first course.
022. Prepare scaffold and material supply
Possible hazards: Falling material, an overloaded platform or poor access can injure masonry and adjacent crews.
Planned controls: Accept the scaffold inspection and permitted loading arrangement. Distribute staged bricks and mortar within those limits, keep access clear and separate the ground zone below. Use the released cutting and mixer resources for prepared supply rather than moving those operations onto the scaffold.
Check before work: Scaffold user lead checks the current platform, material positions and exclusion zone.
033. Lay the supported veneer course
Possible hazards: Repeated handling and wet mortar can cause overexertion, pinch injuries or skin burns.
Planned controls: Work from the protected platform with manageable supply close to use and planned assistance for bulk transfers. Lay specified units and mortar on the released support without leaning over protection; maintain assessed hand, eye and skin protection and washing access.
Check before work: Masonry lead monitors reach, handling and the supported course position.
044. Install specified mechanical ties
Possible hazards: Missing or incorrectly attached ties can allow veneer movement or detachment.
Planned controls: Install the identified ties at the drawing locations into the specified backing support using approved compatible fasteners. Maintain embedment and movement accommodation under the detail, and verify tie attachment before the next courses conceal it. Do not fasten to sheathing alone unless that precise system is designed for it.
Check before work: Lead records tie type, attachment and actual findings at the planned hold points.
055. Maintain cavity and movement details
Possible hazards: Mortar bridging or blocked weeps can defeat drainage and restrain intended movement.
Planned controls: Keep the specified cavity, flashing, weeps and movement-joint spaces clear as work rises. Use the approved debris-control method and maintain any temporary restraint. Stop for altered joints, damaged flashing or a detail that conflicts with an anchor.
Check before work: Lead verifies the concealed details before they become inaccessible.
066. Protect and hand over incomplete work
Possible hazards: Unfinished veneer can move in weather or be mistaken for an accepted facade.
Planned controls: Cover and protect unfinished work under the project’s weather and stability plan without overloading the scaffold. Transfer completed tie and detail records, remaining restrictions and the next-stage release to the receiving lead; retain temporary measures until their designated release.
Check before work: Receiving lead confirms veneer status and unresolved items before adjacent work.
Example scope and starting conditions
A masonry crew will build a low-rise fired-clay brick veneer wythe on a released foundation ledge against completed wood-stud backing. Work uses a handed-over supported scaffold and the approved tie, cavity, flashing and movement-joint details. This fictional learning example describes planned controls; it records no actual inspection or work authorization.
- Vertical support, backing readiness and temporary stability measures are released before the veneer rises.
- The scaffold loading plan governs brick and mortar staging; cutting and mortar mixing use separate controlled stations.
- This excludes load-bearing brickwork, high-rise shelf-angle construction, backing erection and substitution of adhered thin brick for anchored veneer.
Know when to pause
- Ledge, backing or tie attachments cannot be verified against the current design.
- A stability measure, scaffold condition or weather boundary changes.
- Cavity, flashing, weeps or movement details are obstructed or altered.
After a pause, correct the condition, reassess the work, and obtain required authorization before restarting.
Free example and template
No account required. The worked example contains planned controls. The blank template is for your own work; neither includes fabricated inspection results, signatures or approval.
Need help? Ask Jenkins
Jenkins · Your Safety Concierge
What brings you here today? Choose what you’re working on, or tell Jenkins about your situation.
Jenkins matches your words to published starting points. Keep names and private job details in your working draft. Suitable free resources come first.
For managers
Does the team have what it needs to carry out the plan? Give the crew time, equipment and support, and make it clear who will resolve anything that is missing.
Manager checks and supporting resources
Confirm the people doing the work have the time, equipment, information and support to carry out the plan. Agree who checks the controls and who resolves open actions.
Questions to resolve before work
- Who releases the ledge, backing and specified tie attachment locations?
- How will ties, clear cavity, flashing, weeps and movement joints remain visible for verification?
- What temporary stability and scaffold loading restrictions apply during each incomplete stage?
Training and qualifications to confirm
- The actual anchored-veneer tie, cavity, flashing, weep, movement and temporary-stability details.
- Applicable scaffold-user training and task instruction on material staging, wet-mortar contact and safe handling.
Confirm the actual training evidence for the assigned people. A toolbox talk does not establish competence.
Decisions that change the plan
Can the adhered stone veneer sequence be used for these bricks?
No. This brick wythe carries weight on its released ledge and transfers lateral forces through specified mechanical ties to backing. Adhered veneer uses a different attachment system and does not supply those structural or cavity details.
What must the crew record for actual use?
Identify the actual equipment and work boundaries, responsible people, applicable criteria, inspection findings and open actions. Resolve changes with affected crews and obtain required project authorization before work.
Keep planning connected
Resources that support this JHA
Additional tools for task planning and safe work. Start with the free resources; explore paid options only when they meet an additional need.
Toolbox talks for the work
Prepare a practical crew discussion.
Scaffolds: Verify Readiness Before Access →Wet Concrete: Prevent Skin and Eye Contact →Manual Handling: Change the Lift Before You Lift →Safety program resources
Review procedures, roles, and requirements.
Browse the existing catalog and confirm the scope and purchase availability of each program.
Browse safety programs →Paid service · Availability
Task-specific training and qualifications
Explore applicable training and qualification needs.
Task-specific training services are not currently available to book here. Start with the free training-needs lookup; a toolbox talk or online course alone does not establish competence or employer authorization.
Review training needs · Free →People, equipment, emergency arrangements and open actions are recorded in the guided JHA’s Crew review step.
Open the crew review step →For safety professionals
How do we know the planning process and controls are working? Connect what the crew reports with field checks, risk decisions and the evidence behind your system.
Industry context, SIF, control verification and AHA review
Guidance and evidence
Review the method, risk decisions and evidence behind the plan. Use the actual jurisdiction, equipment instructions, employer process and project requirements.
Task-by-task control and verification rationale
1. Accept support and backing
Hazard: An inadequate ledge or unready backing can leave the veneer without its intended load path.
Control: Masonry lead checks the ledge, completed backing and current veneer details with the responsible framing or facade lead. Establish the applicable masonry access restriction and temporary stability arrangements; hold construction where support or anchorage is unresolved.
Verification: Lead records the receiving-interface release before laying the first course.
Why this belongs in the analysis: The veneer’s weight and lateral restraint follow different structural paths.
2. Prepare scaffold and material supply
Hazard: Falling material, an overloaded platform or poor access can injure masonry and adjacent crews.
Control: Accept the scaffold inspection and permitted loading arrangement. Distribute staged bricks and mortar within those limits, keep access clear and separate the ground zone below. Use the released cutting and mixer resources for prepared supply rather than moving those operations onto the scaffold.
Verification: Scaffold user lead checks the current platform, material positions and exclusion zone.
Why this belongs in the analysis: A wall detail does not establish a safe masonry work platform.
3. Lay the supported veneer course
Hazard: Repeated handling and wet mortar can cause overexertion, pinch injuries or skin burns.
Control: Work from the protected platform with manageable supply close to use and planned assistance for bulk transfers. Lay specified units and mortar on the released support without leaning over protection; maintain assessed hand, eye and skin protection and washing access.
Verification: Masonry lead monitors reach, handling and the supported course position.
Why this belongs in the analysis: Small repeated lifts and contact exposures accumulate through the shift.
4. Install specified mechanical ties
Hazard: Missing or incorrectly attached ties can allow veneer movement or detachment.
Control: Install the identified ties at the drawing locations into the specified backing support using approved compatible fasteners. Maintain embedment and movement accommodation under the detail, and verify tie attachment before the next courses conceal it. Do not fasten to sheathing alone unless that precise system is designed for it.
Verification: Lead records tie type, attachment and actual findings at the planned hold points.
Why this belongs in the analysis: A visible metal strip is not proof of a completed load transfer.
5. Maintain cavity and movement details
Hazard: Mortar bridging or blocked weeps can defeat drainage and restrain intended movement.
Control: Keep the specified cavity, flashing, weeps and movement-joint spaces clear as work rises. Use the approved debris-control method and maintain any temporary restraint. Stop for altered joints, damaged flashing or a detail that conflicts with an anchor.
Verification: Lead verifies the concealed details before they become inaccessible.
Why this belongs in the analysis: Later face cleaning cannot restore an obstructed hidden cavity.
6. Protect and hand over incomplete work
Hazard: Unfinished veneer can move in weather or be mistaken for an accepted facade.
Control: Cover and protect unfinished work under the project’s weather and stability plan without overloading the scaffold. Transfer completed tie and detail records, remaining restrictions and the next-stage release to the receiving lead; retain temporary measures until their designated release.
Verification: Receiving lead confirms veneer status and unresolved items before adjacent work.
Why this belongs in the analysis: Completion of a course does not release every support or weather restriction.
Compare control wording
| Needs improvement | More useful for this scenario |
|---|---|
| Work carefully and wear PPE. | Work from the protected platform with manageable supply close to use and planned assistance for bulk transfers. Lay specified units and mortar on the released support without leaning over protection; maintain assessed hand, eye and skin protection and washing access. |
| Check that everything is ready. | Masonry lead checks the ledge, completed backing and current veneer details with the responsible framing or facade lead. Establish the applicable masonry access restriction and temporary stability arrangements; hold construction where support or anchorage is unresolved. |
Common questions
Can this example be used as a JSA?
Adapt its Task | Hazard | Control analysis to the employer’s format and actual conditions. The example is a teaching aid, not evidence that controls were checked.
What changes if the project requires an AHA?
Use the governing AHA format, risk method, supporting records and acceptance process. The published formwork AHA demonstrates that additional structure; changing a JHA title does not supply it.
Are these resources part of a paid course?
This walkthrough, browser draft builder and downloads are free public resources, separate from Academy course enrollment.
References and source note
- BIA Technical Note 28: Brick veneer wood stud walls
- OSHA 1926.706 Masonry construction
- OSHA 1926.451 Scaffold requirements
Original instructional scenario with planned controls. Primary references support hazard planning. Use actual equipment and product instructions, project design and employer requirements to establish field criteria. Use actual equipment instructions and site requirements alongside these references. Reference review: October 9, 2026.