Site-Built Structural Brick Arch JHA
A JHA breaks the work into steps, hazards and controls. Use this example to build a draft for your actual job and review it with your crew.
Just need the example? Download it here.For the crew
You know the work. Let’s turn that experience into a plan your crew can talk through. Start with today’s job, then check the steps together.
Let’s build your JHA.
Step 1 of 4 · Working draft
Your job
Tell Jenkins what you’re planning and where the work will happen. Use the actual job details.
Use the published example’s suggestions when they fit your task, or write your own steps. These are planned controls, not verified worksite conditions.
Describe an observable step, how someone could be harmed, and the control that acts on that hazard. Identify who checks it and what evidence is needed.
Walk through the plan with the people doing the work. Resolve missing controls and agree who checks them. Moving to the next step does not approve the work.
Confirm people, equipment and emergency arrangements
Record changes, checks, and open actions
Walk the work area, review with the crew, and resolve missing controls. Follow the required approval process. This tool does not judge completeness, verify signatures or authorize work.
Print your own JHA by signing in, or contribute the selected structured categories as a guest. Signing in does not require research participation. Written job details are processed to prepare your export and are stored on our server only if you save to your private company library.
Research purpose, data fields, retention and withdrawal · Privacy notice
Sign-in uses a free account. Your tab draft is retained for the return from sign-in.
Hosted organization saving requires active jSMS access and a company workspace. View jSMS plans.
The export uses landscape pages, task-only continuation pages and a Page X of Y footer in current Chrome or Edge. Review every page. Opening an export is not proof that the JHA was printed or used. The PDF includes its research choice and reference; the private withdrawal link stays in the export’s screen-only receipt.
Device storage and other draft options
Device copies may contain private job information. Clear them when using a shared device.
Your entries stay in this working draft as you move between steps. Required field checks, employer review and work authorization remain separate.
Your Site-Built Structural Brick Arch JHA
Walk through the job in order. Use these possible hazards, planned controls and checks to start a conversation about your actual work.
011. Release the structural arch package
Possible hazards: A decorative detail or unverified abutment can be mistaken for an arch capable of carrying structural loads.
Planned controls: Masonry lead matches the opening, arch and surrounding masonry to the engineer-issued detail. Verify abutment and thrust-restraint acceptance and identify current stage/load limits. Refer missing structural criteria or changed geometry before work; a brick technical note is supporting guidance, not this opening’s design.
Check before work: Lead checks the design identity and actual abutment/restraining construction at release.
022. Accept centering and safe work positions
Possible hazards: An unstable support or unsafe opening edge can cause falls or collapse before the arch is complete.
Planned controls: Obtain the separate centering acceptance and check the actual profile, contact, restraint and permitted loads against its issued arrangement. Provide protected access and controlled areas on both sides of the opening. Keep stock off unapproved support locations and preserve every required brace throughout masonry construction.
Check before work: Responsible lead checks centering status, access and staging before placing the first units.
033. Lay out units and stage mortar
Possible hazards: Poor unit spacing or unsuitable materials can create uneven joints; sharp edges and wet mortar expose workers.
Planned controls: Identify the specified units, orientation and mortar system, and set out the released arch layout on the accepted centering. Stage manageable quantities and suitable placement tools from stable positions. Use assessed skin/eye protection and washing arrangements; hold an unresolved unit or joint mismatch instead of cutting a new design on site.
Check before work: Masonry lead compares the layout and product identities with the actual detail.
044. Build the arch in the issued sequence
Possible hazards: Unbalanced construction or unfilled structural joints can compromise the arch and overload temporary support.
Planned controls: Place units in the design’s stated sequence and orientation while maintaining centering and any required restraint. Form and fully fill the specified joints with the selected mortar, keeping hands outside closing gaps. Check progressing geometry and stage loading; stop for support movement or a joint/shape conflict rather than forcing a unit into place.
Check before work: Lead records unit arrangement, joint filling and support response at the planned hold points.
055. Close and complete the designated masonry stage
Possible hazards: Premature disturbance at closure or loading from adjacent work can damage the newly completed arch.
Planned controls: Complete the specified closing units and designated surrounding masonry under the issued sequence. Inspect geometry, joints and support condition before concealment, maintaining restricted loading and cure protection. Do not ease the centering, wedge the arch or add construction loads unless a separately accepted procedure specifically authorizes that change.
Check before work: Designated reviewer checks actual closure and stage-completion findings against the design.
066. Protect cure and transfer support restrictions
Possible hazards: Elapsed time or finished appearance can be misused as authority to remove centering and reopen access.
Planned controls: Protect the arch and surrounding masonry under the actual weather, curing and loading plan. Transfer material, construction and inspection records, unresolved items and the required strength/support-release criteria. Retain centering and boundaries until the responsible acceptance process releases a separate transfer/removal sequence; no common number of days supplies that decision.
Check before work: Receiving lead confirms curing/load restrictions and who can authorize support changes.
Example scope and starting conditions
A masonry crew will build one engineer-designed true structural brick arch over a ground-floor opening in a new low-rise building. Released abutments and separately accepted centering support the specified arch units and surrounding masonry sequence. Work ends with completed masonry protected for strength and loading acceptance; centering easing or removal is separate. This fictional learning example describes planned controls; it records no actual inspection or work authorization.
- The structural design identifies arch geometry, abutment/thrust restraint, unit orientation, mortar, joint arrangement, surrounding masonry sequence and temporary-support/loading criteria.
- Centering is separately designed, erected and accepted; protected work positions, both-side access control and permitted staging loads are released before units are placed.
- Partial bricklaying and structural-wall coverage: no decorative veneer-only arch, precast lintel setting, field arch design, centering fabrication or premature support removal.
Know when to pause
- Arch geometry, abutment restraint, centering or required structural documents differs from the release.
- Units or joints cannot meet the detail, support moves or construction loading exceeds the accepted stage.
- The request introduces field design, a veneer-only detail, early loading, centering easing or support removal.
After a pause, correct the condition, reassess the work, and obtain required authorization before restarting.
Free example and template
No account required. The worked example contains planned controls. The blank template is for your own work; neither includes fabricated inspection results, signatures or approval.
Need help? Ask Jenkins
Jenkins · Your Safety Concierge
What brings you here today? Choose what you’re working on, or tell Jenkins about your situation.
Jenkins matches your words to published starting points. Keep names and private job details in your working draft. Suitable free resources come first.
For managers
Does the team have what it needs to carry out the plan? Give the crew time, equipment and support, and make it clear who will resolve anything that is missing.
Manager checks and supporting resources
Confirm the people doing the work have the time, equipment, information and support to carry out the plan. Agree who checks the controls and who resolves open actions.
Questions to resolve before work
- What releases the actual abutments and thrust restraint for this arch and its construction stages?
- How will centering, unit arrangement and joints be checked before the arch is closed?
- Who determines strength/loading acceptance and the separate support-transfer or centering-removal sequence?
Training and qualifications to confirm
- The actual structural arch detail, centering restrictions, unit/joint layout, closure sequence and construction-stage loading limits.
- Masonry handling and wet-mortar contact protection, safe access around the opening and recognition of movement requiring immediate withdrawal and review.
Confirm the actual training evidence for the assigned people. A toolbox talk does not establish competence.
Decisions that change the plan
Is this equivalent to installing a precast lintel?
No. The lintel arrives as one designed spanning component and is seated on bearings. This crew constructs an arch whose geometry, filled joints, abutment restraint and temporary centering develop a different load path. A decorative curved veneer course is also not this structural arch.
What must the crew record for actual use?
Record the actual work boundary, equipment and materials, responsible people, applicable criteria, control checks and unresolved actions. Keep changed conditions on hold, communicate restrictions to affected crews and obtain the required project authorization before work.
Keep planning connected
Resources that support this JHA
Additional tools for task planning and safe work. Start with the free resources; explore paid options only when they meet an additional need.
Toolbox talks for the work
Prepare a practical crew discussion.
Wet Concrete: Prevent Skin and Eye Contact →Manual Handling: Change the Lift Before You Lift →Barricades: What Does This Boundary Keep Out? →Safety program resources
Review procedures, roles, and requirements.
Browse the existing catalog and confirm the scope and purchase availability of each program.
Browse safety programs →Paid service · Availability
Task-specific training and qualifications
Explore applicable training and qualification needs.
Task-specific training services are not currently available to book here. Start with the free training-needs lookup; a toolbox talk or online course alone does not establish competence or employer authorization.
Review training needs · Free →People, equipment, emergency arrangements and open actions are recorded in the guided JHA’s Crew review step.
Open the crew review step →For safety professionals
How do we know the planning process and controls are working? Connect what the crew reports with field checks, risk decisions and the evidence behind your system.
Industry context, SIF, control verification and AHA review
Guidance and evidence
Review the method, risk decisions and evidence behind the plan. Use the actual jurisdiction, equipment instructions, employer process and project requirements.
Task-by-task control and verification rationale
1. Release the structural arch package
Hazard: A decorative detail or unverified abutment can be mistaken for an arch capable of carrying structural loads.
Control: Masonry lead matches the opening, arch and surrounding masonry to the engineer-issued detail. Verify abutment and thrust-restraint acceptance and identify current stage/load limits. Refer missing structural criteria or changed geometry before work; a brick technical note is supporting guidance, not this opening’s design.
Verification: Lead checks the design identity and actual abutment/restraining construction at release.
Why this belongs in the analysis: A structural arch develops forces in its supports as well as within its brickwork.
2. Accept centering and safe work positions
Hazard: An unstable support or unsafe opening edge can cause falls or collapse before the arch is complete.
Control: Obtain the separate centering acceptance and check the actual profile, contact, restraint and permitted loads against its issued arrangement. Provide protected access and controlled areas on both sides of the opening. Keep stock off unapproved support locations and preserve every required brace throughout masonry construction.
Verification: Responsible lead checks centering status, access and staging before placing the first units.
Why this belongs in the analysis: The unfinished arch relies on temporary support throughout its developing geometry.
3. Lay out units and stage mortar
Hazard: Poor unit spacing or unsuitable materials can create uneven joints; sharp edges and wet mortar expose workers.
Control: Identify the specified units, orientation and mortar system, and set out the released arch layout on the accepted centering. Stage manageable quantities and suitable placement tools from stable positions. Use assessed skin/eye protection and washing arrangements; hold an unresolved unit or joint mismatch instead of cutting a new design on site.
Verification: Masonry lead compares the layout and product identities with the actual detail.
Why this belongs in the analysis: A planned layout identifies fit conflicts before they are locked into a structural assembly.
4. Build the arch in the issued sequence
Hazard: Unbalanced construction or unfilled structural joints can compromise the arch and overload temporary support.
Control: Place units in the design’s stated sequence and orientation while maintaining centering and any required restraint. Form and fully fill the specified joints with the selected mortar, keeping hands outside closing gaps. Check progressing geometry and stage loading; stop for support movement or a joint/shape conflict rather than forcing a unit into place.
Verification: Lead records unit arrangement, joint filling and support response at the planned hold points.
Why this belongs in the analysis: Appearance at the exposed face does not establish complete structural joint filling.
5. Close and complete the designated masonry stage
Hazard: Premature disturbance at closure or loading from adjacent work can damage the newly completed arch.
Control: Complete the specified closing units and designated surrounding masonry under the issued sequence. Inspect geometry, joints and support condition before concealment, maintaining restricted loading and cure protection. Do not ease the centering, wedge the arch or add construction loads unless a separately accepted procedure specifically authorizes that change.
Verification: Designated reviewer checks actual closure and stage-completion findings against the design.
Why this belongs in the analysis: A closed arch ring does not by itself establish sufficient strength for all imposed loads.
6. Protect cure and transfer support restrictions
Hazard: Elapsed time or finished appearance can be misused as authority to remove centering and reopen access.
Control: Protect the arch and surrounding masonry under the actual weather, curing and loading plan. Transfer material, construction and inspection records, unresolved items and the required strength/support-release criteria. Retain centering and boundaries until the responsible acceptance process releases a separate transfer/removal sequence; no common number of days supplies that decision.
Verification: Receiving lead confirms curing/load restrictions and who can authorize support changes.
Why this belongs in the analysis: The construction-stage load path persists until the required structural acceptance is complete.
Compare control wording
| Needs improvement | More useful for this scenario |
|---|---|
| Follow a curved row and remove the timber when it looks finished. | Use the designed arch and abutments on accepted centering, record the completed masonry stage and retain support until its specified structural release. |
| A neat face means the joints are adequate. | Verify specified unit orientation and full structural joint filling at the construction hold points, including parts that later masonry would conceal. |
Common questions
Can this example be used as a JSA?
Adapt the Task | Hazard | Control sequence to the employer’s JSA format and actual worksite. Name the people who will check controls and record their findings; this learning example supplies no completed field inspection.
What changes if the project requires an AHA?
Use the governing AHA format, risk method, supporting records and acceptance process. The published formwork AHA illustrates that additional structure. Add the actual competencies, inspections and project reviews rather than assuming a renamed JHA meets those requirements.
Are these resources part of a paid course?
This walkthrough, browser draft builder and downloads are free public resources, separate from Academy course enrollment.
References and source note
- BIA Technical Note 31 Brick masonry arches
- OSHA 1926.706 Masonry construction
- OSHA 1926.501 Duty to have fall protection
Original instructional scenario with planned controls. Primary references support hazard planning. Use actual equipment and product instructions, project design and employer requirements to establish field criteria. This example supplies no inspection findings or work authorization. Use actual equipment instructions and site requirements alongside these references. Reference review: October 9, 2026.
Developed by Todd Jerome Jenkins, MS, CSP · Edition v1.0 · October 13, 2026
Use the builder’s Print / Save as PDF action after signing in or accepting research participation.